CALIBRATION OF WATER DISTRIBUTION NETWORKS

Ebat: px
Şu sayfadan göstermeyi başlat:

Download "CALIBRATION OF WATER DISTRIBUTION NETWORKS"

Transkript

1 CALIBRATION OF WATER DISTRIBUTION NETWORKS A THESIS SUBMITTED TO THE GRADUATE SCHOOL OF NATURAL AND APPLIED SCIENCES OF MIDDLE EAST TECHNICAL UNIVERSITY BY KEREM AR IN PARTIAL FULFILLMENT OF THE REQUIREMENTS FOR THE DEGREE OF MASTER OF SCIENCE IN CIVIL ENGINEERING DECEMBER 2011

2 Approval of the thesis: CALIBRATION OF WATER DISTRIBUTION NETWORKS submitted by KEREM AR in partial fulfillment of the requirements for the degree of Master of Science in Civil Engineering Department, Middle East Technical University by, Prof. Dr. Canan Özgen Dean, Graduate School of Natural and Applied Sciences Prof. Dr. Güney Özcebe Head of Department, Civil Engineering Assoc. Prof. Dr. Nuri Merzi Supervisor, Civil Engineering Dept., METU Examining Committee Members: Assoc. Prof. Dr. S. Zuhal Akyürek Civil Engineering Dept., METU Assoc. Prof. Dr. Nuri Merzi Civil Engineering Dept., METU Assoc. Prof. Dr. A. Burcu Altan Sakarya Civil Engineering Dept., METU Assoc. Prof. Dr. Elçin Kentel Civil Engineering Dept., METU Gökhan Bağcı (Env.E., M.Sc) ASKİ Date:

3 I hereby declare that all information in this document has been obtained and presented in accordance with academic rules and ethical conduct. I also declare that, as required by these rules and conduct, I have fully cited and referenced all material and results that are not original to this work. Name, Last Name : KEREM AR Signature : iii

4 1. ABSTRACT CALIBRATION OF WATER DISTRIBUTION NETWORKS Ar, Kerem M.Sc., Department of Civil Engineering Supervisor: Assoc. Prof. Dr. Nuri Merzi December 2011, 116 pages Water distribution network models are used for different purposes. In this study, a model, used for daily operational issues is concerned. Models results should be consistent with actual conditions for sound decisions during operational studies. Adjusting model parameters according to site measurements in order to fit the model to obtain realistic results is known as calibration. Researchers have carried out numerous studies on calibration and developed various methods. In this study, an actual network (N8.3 Pressure Zone, Ankara) has been calibrated by two classical methods developed by Walski (1983) and Bhave (1988). The network parameter calibrated in this study is Hazen-Williams roughness coefficient, C-factor, and other parameters have been lumped in the C-factor. Results of the analysis showed that, C- factors have been found in a wide range. Keywords: Water Distribution, Hydraulic Network Model, Calibration, Water Distribution Network of City of Ankara, Case Study iv

5 ÖZ SU DAĞITIM ŞEBEKELERİNİN KALİBRASYONU Ar, Kerem Yüksek Lisans, İnşaat Mühendisliği Bölümü Tez Yöneticisi: Doç. Dr. Nuri Merzi Aralık 2011, 116 sayfa Su dağıtım şebekelerinin modelleri farklı amaçlar için kullanılır. Bu çalışmada günlük işletme amaçlı kullanılan bir model göz önünde bulundurulmuştur. İşletme sırasında doğru kararlar verebilmek için model sonuçlarının gerçek değerlerle tutarlı olması gerekmektedir. Model parametrelerinin, modelin gerçekçi sonuçlar vermesini sağlayacak şekilde ayarlanmasına kalibrasyon denilir. Araştırmacılar kalibrasyon hakkında çok sayıda çalışma yapmışlar ve çeşitli yöntemler geliştirmişlerdir. Bu çalışmada gerçek bir su dağıtım şebekesi (N8.3 Basınç Bölgesi, Ankara) Walski (1983) ve Bhave (1988) tarafından geliştirilen iki klasik yöntem kullanılarak kalibre edilmiştir. Çalışmada kalibre edilen model parametresi Hazen-Williams pürüzlülük katsayısı olan C katsayısıdır ve diğer parametreler de C katsayısının içinde değerlendirilmiştir. Analizler sonucunda C katsayıları geniş bir aralıkta bulunmuştur. Anahtar Kelimeler: Su Dağıtım Şebekesi, Şebeke Hidrolik Modeli, Kalibrasyon, Ankara Şehri Su Dağıtım Şebekesi, Durum Çalışması v

6 To My Family... vi

7 2. ACKNOWLEDGEMENTS I would like to state that I am grateful to my advisor Assoc. Prof. Dr. Nuri Merzi for his contributions, arrangements for the field works and his attention at every stage of the study. I would also express my kind gratitude to Halil Şendil and Onur Bektaş for their contributions and peerless assistance at field works. I am also thankful to my dear friends Onur Arı and Musa Yılmaz who provided great motivation and guidance during this study. vii

8 3. TABLE OF CONTENTS ABSTRACT... iv ÖZ... v ACKNOWLEDGEMENTS... vii TABLE OF CONTENTS... viii LIST OF FIGURES... xi LIST OF TABLES...xiii 1. INTRODUCTION General Scope of the Study LITERATURE REVIEW Definitions of Calibration in the Literature Standards for Calibration Calibration Applications for Real Networks Determination of Test Node Locations Sources of Error in Modeling Nominal vs. Actual Pipe Diameter Internal Pipe Roughness Values Distribution System Demands System Maps Temporal Boundary Conditions Pump Characteristic Curves Data Preparation Skeletonization of Network Head at Source Nodes viii

9 2.6.3 Supply at Source Nodes Consumption at Demand Nodes Pipe Head Loss Coefficients Proposed Methods for Calibration THEORETICAL CONSIDERATIONS General Walski s Method (1983) Development of the Method Calibration of an Example System Bhave s Method (1988) Development of the Method Calibration of the Example System Application of the Method in the Case Study FIELD WORKS Establishment of the Model Construction Works Determination of Valve Locations Installation of Fire Hydrants Construction of Measurement Chambers Isolation of Sub-Zones Utilization of GIS Site Tests Topographic Position Measurements Measurement of Coordinates of Measurement Chambers Measurement of Coordinates of Test Node Taps Pressure Measurements The Setup Measurements Discharge Measurements ix

10 5. CASE STUDY: MODEL CALIBRATION OF N8.3 PRESSURE ZONE, ANKARA General Information About N8.3 Pressure Zone Hydraulic Model Calibration of N Calibration of Yayla Network Model Walski s (1983) Method Bhave s (1988) Method Calibration of North Sancaktepe Network Model Walski s (1983) Method Bhave s (1988) Method Calibration of South Sancaktepe Network Model Walski s (1983) Method Bhave s (1988) Method Calibration of Şehit Kubilay Network Model Walski s (1983) Method Bhave s (1988) Method Calibration of Upper Çiğdemtepe Network Model Walski s (1983) Method Bhave s (1988) Method Calibration of Lower Çiğdemtepe Network Model Walski s (1983) Method Bhave s (1988) Method CONCLUSIONS AND RECOMMENDATIONS BIBLIOGRAPHY APPENDIX A APPENDIX B x

11 4. LIST OF FIGURES FIGURES Figure 2.1 Tuberculated Pipe Section ( 8 Figure 2.2 Distribution of Demands on Pipes... 9 Figure 2.3 Sample Flow Measurement Figure 3.1 Example System for Walski s (1983) Method Figure 3.2 An Illustrative Figure (Bhave, 1988) Figure 3.3 Example System Figure 3.4 Adjustment Zones and Path for Yayla Figure 4.1 Asphalt Covered Measurement Chamber Cover Figure 4.2 A Valve Cover Figure 4.3 Fire Hydrant Figure 4.4 A Measurement Chamber Figure 4.5 GPS Measurement Figure 4.6 Fire Hose Setup Figure 4.7 Strainer and Discharge Pipe Figure 4.8 Digital Manometer Figure 4.9 Ultrasonic Flowmeter Figure 5.1 Satellite View of N8.3 (Google) Figure 5.2 Sub-Zones of N Figure 5.4 Yayla Sub-Zone (2/2) Figure 5.5 North Sancaktepe Sub-Zone (1/2) Figure 5.6 North Sancaktepe Sub-Zone (2/2) Figure 5.7 South Sancaktepe Sub-Zone (1/2) Figure 5.8 South Sancaktepe Sub-Zone (2/2) xi

12 Figure 5.9 Şehit Kubilay Sub-Zone (1/3) Figure 5.10 Şehit Kubilay Sub-Zone (2/3) Figure 5.11 Şehit Kubilay Sub-Zone (3/3) Figure 5.12 Upper Çiğdemtepe Sub-Zone Figure 5.13 Lower Çiğdemtepe Sub-Zone (1/2) Figure 5.14 Lower Çiğdemtepe Sub-Zone (2/2) xii

13 5. LIST OF TABLES TABLES Table 3.1 Interpretation of a and b (Walski, 1983) Table 3.2 Pipe Properties of the Example System Table 3.3 Estimated Nodal Demands for Example System Table 3.4 Summary of Iterations of Walski s (1983) Method for the Example System Table 3.5 Pipe Properties of Example System Table 3.6 Estimated Nodal Demands for Example System Table 3.7 Observed Hydraulic Grades in the Field Tests Table 3.8 Summary of Results of Equations for Example System Table 4.1 Coordinates of Test Nodes and Measurement Chambers Table 4.2 Pressure Measurements Table 4.3 Discharge Measurements Table 4.4 Summary of the Measurements (Set-1) Table 4.5 Summary of the Measurements (Set-2) Table 5.1 Test Observations for Yayla Sub-Zone Table 5.2 Summary of Iterations of Walski s (1983) Method for Yayla Sub-Zone for Data Set Table 5.3 Summary of Iterations of Walski s (1983) Method for Yayla Sub-Zone for Data Set Table 5.4 Summary of Iterations of Bhave s (1988) Method for Yayla Sub-Zone Table 5.5 Test Observations for North Sancaktepe Sub-Zone xiii

14 Table 5.6 Summary of Iterations of Walski s (1983) Method for North Sancaktepe Sub-Zone for Data Set Table 5.7 Summary of Iterations of Walski s (1983) Method for North Sancaktepe Sub-Zone for Data Set Table 5.8 Summary of Iterations of Bhave s (1988) Method for North Sancaktepe Sub-Zone Table 5.9 Test Observations for South Sancaktepe Sub-Zone Table 5.10 Summary of Iterations of Walski s (1983) Method for South Sancaktepe Sub-Zone for Data Set Table 5.11 Summary of Iterations of Bhave s (1988) Method for South Sancaktepe Sub-Zone Table 5.12 Test Observations for Şehit Kubilay Sub-Zone Table 5.13 Summary of Iterations of Walski s (1983) Method for Şehit Kubilay Sub-Zone for Data Set Table 5.14 Summary of Iterations of Walski s (1983) Method for Şehit Kubilay Sub-Zone for Data Set Table 5.15 Summary of Iterations of Bhave s (1988) Method for Şehit Kubilay Sub-Zone Table 5.16 Test Observations for Upper Çiğdemtepe Sub-Zone Table 5.17 Summary of Iterations of Walski s (1983) Method for Upper Çiğdemtepe Sub-Zone for Data Set Table 5.18 Summary of Iterations of Walski s (1983) Method for Upper Çiğdemtepe Sub-Zone for Data Set Table 5.19 Summary of Iterations of Bhave s (1988) Method for Upper Çiğdemtepe Sub-Zone Table 5.20 Test Observations for Lower Çiğdemtepe Sub-Zone xiv

15 Table 5.21 Summary of Iterations of Walski s (1983) Method for Lower Çiğdemtepe Sub-Zone for Data Set Table 5.22 Summary of Iterations of Walski s (1983) Method for Lower Çiğdemtepe Sub-Zone for Data Set Table 5.23 Summary of Iterations of Bhave s (1988) Method for Lower Çiğdemtepe Sub-Zone Table A.1 Pipe Properties of Yayla Sub-Zone xv

16 CHAPTER 1 1. INTRODUCTION 1.1 General Water resources are becoming scarce nowadays as a result of increasing population, and contamination in potable water resources. So, effective usage and operation of water resources is gaining importance. In this sense, water distribution networks should be operated efficiently; an adequate operation should be based on a correct model. Different types of models are used according to the scopes of studies. These are long range master planning, rehabilitation, fire protection studies, water quality investigations, energy management, daily operations, and troubleshooting (Walski et al., 2003). Mathematical models are useful for simulation of distribution networks. These models are not only used in the design stage of a project, but also they play a great role in operation of the systems. Water distribution network (WDN) models consist of several elements, such as pipes, pumps, tanks, and valves. So, characteristics of each element have a considerable effect on the behavior of the system. Loading conditions, tank elevations, pump and valve status may change within the day. So that, the operators should forecast how those changes may affect the network. Network models are also studied for extended period simulations (EPS) of WDNs, which are beneficial for predicting the response of the system when unexpected cases occur. 1

17 Although new water distribution systems are designed by means of mathematical models nowadays, a great majority of existing water distribution networks have not been modeled. In order to simulate such networks in operational studies, their models should be built. Such models are established by using city maps and network plans, and sometimes by using verbal knowledge of administration staff. In some situations, actual case may be different from network plan drawings. From the construction of network to modeling stage, there may have been changes in networks. Such changes can occur in two ways; first changes came up with time, like aging of pipes; and second non-recorded (new furnished pipes or consumer connections) or abandoned (asphalt covered and forgotten closed valves) changes applied by water utilities. Thus, some adjustments in the model elements are necessary for accurate representation of actual conditions. The work of adjusting model parameters such as roughness coefficients and nodal demands for adequate representation of existing situation is called calibration. During calibration studies, several steps should be followed in order to obtain realistic results. The first step is determination of pipes and valve locations, and then making the valves available for operation. Second, establishment of isolated sub-zones is necessary in order to reduce the complexity of the system. During this step, necessary facilities like source and test nodes should also be determined. Then, field tests like pressure and discharge measurements should be carried out to obtain necessary information. Finally, a number of analyses are to be carried out with any selected method. In general, two major parameters of network models are calibrated which are roughness coefficients like Hazen-Williams C-factor, and water consumption at demand nodes. On the other hand, if total amount of flow entering the network can be measured accurately, importance of the adjustments in nodal 2

18 demands decreases. Thus, C-factor becomes a lumped parameter including all causes of head losses such as closed valves, minor losses like bends and partially open valves, or nodal demands in addition to pipe friction. 1.2 Scope of the Study The aim of this study is to calibrate an actual WDN and to indicate necessary works which should be carried out for calibration. A brief information about the study has been given in Chapter 1. The literature review relevant to water distribution network calibration has been discussed in Chapter 2. In Chapter 3, theoretical considerations of calibration methods used in this study have been explained with examples. Works done before and during field tests like constructions and measurements have been discussed in Chapter 4. In Chapter 5, a case study has been conducted by calibrating a real water distribution network; six sub-zones of N8.3 pressure zone of WDN of City of Ankara are considered. Finally in Chapter 6, conclusions drawn from this study and recommendations for future studies have been presented. 3

19 CHAPTER 2 2. LITERATURE REVIEW Researchers dealing with water supply and distribution have realized importance of calibrated hydraulic modeling studies considering WDNs since early 80s and numerous calibration techniques have been proposed up to now. Nowadays, methods for model calibration are still being developed. 2.1 Definitions of Calibration in the Literature In the studies, various definitions were discussed about calibration based on similar principles. Shamir and Howard (1977) defined calibration as determining physical and operational characteristics of an existing system and input data which would lead realistic results when put into hydraulic model. Walski (1983) defined calibration as a two step process. The first step is the comparison of predicted pressures and flows with observed pressures and flows for known operating conditions i.e., pump operation tank levels, pressure reducing valve settings. The second step is adjustment of the input data to improve agreement between observed and predicted values. Cesario and Davis (1984) stated that calibration is fine tuning a model until it simulates field conditions accurately. Similarly, Speight and Khanal (2009) stated that model calibration is adjusting parameters accurately in order to represent actual conditions with model simulations. 4

20 Although various definitions have been made by many authors for calibration of water distribution systems, there was an agreement on a common point. That point is the consistency of model results with actual observations and well representing of actual conditions. 2.2 Standards for Calibration Since models are complicated and used for many purposes, accuracy and scope of calibration depends on what extent the studies are carried on (Walski, 1995). So, applying strict rules while calibrating network models may not always be reasonable. Instead of this, degree and scope of calibration should be determined, and following tasks should be carried out with this aspect. The important issue is having a model that decision makers can confidently base their decisions on the results of the model (Walski, 1995). Different scopes of model calibration was described by Walski (1995) such as pipe sizing for master planning, extended period simulations for planning studies, subdivision layout, rehabilitation and energy usage studies, water quality models and flushing problems. For these studies, it was recommended that difference between observed and predicted hydraulic grade level (HGL) should be less than a few feet (under fire flow conditions), except master planning studies in which an error up to 5 ft would be acceptable (Walski, 1995). Walski (1995) also explained the role of head loss on accuracy of calibration and had given the following numerical example. Considering the flow in a 20,000 ft long pipe with 12 in diameter is measured to be 200 gpm and measured head loss is 5 ft with ± 3 ft accuracy, the C-factor can be anywhere between 70 and 148. If the flow is increased to 1,000 gpm, then the head loss becomes 99 ft ± 3 ft. In this case, range for C-factor narrows down to 89 and 92. 5

21 2.3 Calibration Applications for Real Networks Speight and Khanal (2009) have researched the current usage of modeling and calibration in the United States. In this study, current modeling applications, model input data, calibration data and model calibration have been considered. The study was based on ten water utilities with serving a population varying between 70,000 to more than one million. All of the utilities had used network models at least once a month for various applications. Moreover, five of the utilities had used models daily, and this was accepted as a high degree of model utilization. Two thirds of the participants had used Geographic Information Systems (GIS) as data source and had been working to convert old skeletonized models to more detailed models with EPS (Speight and Khanal, 2009). Nearly all of the participants had used manufacturers pump curves which were verified by recent pump tests. Nodal demands had been distributed to nodes by using electronic customer billing data obtained from GIS demand allocation. Although many of the participants in the study of Speight and Khanal (2009) have had varying degrees of SCADA (Supervisory Control and Data Acquisition) system, utilities had mostly used traditional hydrant tests as calibration data. In the research, it was reported that most of the participants had pursued macro level (transmission line) calibration focusing on pumps and tanks by using SCADA measurement rather than field tests. Also, the participants declared that macro level calibration was satisfactory for planning and operational type of applications. On the other hand, detailed micro level calibration had been applied by utilities with more experience on modeling rather than the participants building their first models. Speight and Khanal (2009) finally recommended for academic researchers to develop ways for data collection, model development, and calibration besides advanced techniques for water 6

22 utilities without capabilities to invest in expensive software and skilled modeling expertise. 2.4 Determination of Test Node Locations Determination of optimal number and locations of test nodes for calibration studies has been conducted in some studies in the literature. Meier and Barkdoll (2000) developed a method for optimizing the locations of test hydrants in which genetic algorithms (GA) had been applied. Aim of this method is to maximize the number of pipes carrying flow over a specified velocity. Since velocity of flow is the major factor of head loss, the method helps the user maximize head loss from the source to the test node as discussed before. Thus, the results obtained from calibration studies are expected to be found in a narrow range. de Schaetzen, et al. (2000) applied three methods for sampling design. The first and the second methods depended on shortest path algorithms, whereas third method used genetic algorithms for solving optimization problem based on the Shannon s entropy function. Kapelan et al. (2003) used multi objective genetic algorithms for determining optimal locations of test nodes. Objective functions of the method are minimizing uncertainty of calibrated model and minimizing the cost of sampling design. Such approaches have not been applied in this study, because there is only one hydrant for each sub-zone. 2.5 Sources of Error in Modeling For water distribution networks, making an error-free study is impossible because there are many uncertainties. Walski et al. (2003) pointed out 7

23 possible sources of error in network modeling. Such errors are possible reasons of anomalies such as too high or low C-factors in calibration results Nominal vs. Actual Pipe Diameter Nominal pipe diameters are equal to the actual diameters in the early ages of WDNs. Excessive tuberculation may lead to reduction in diameter which may result in increase of head loss values, so it is not reasonable to express such cases with low C-factors as A highly tuberculated pipe section can be seen in Figure 2.1 (Walski et al., 2003). Figure 2.1 Tuberculated Pipe Section ( However, actual diameter differences can be lumped in C-factor, because it is an indicator of anomalies in a network Internal Pipe Roughness Values A great deal of researches have been conducted in order to estimate pipe roughness coefficient values. Lamont (1981) developed a detailed table for 8

24 estimation of pipe roughness for a variety of pipe materials, sizes and ages. Also, Walski et al. (1989) notified the effect of water quality on aging of pipes. Walski et al. (2003) stated that there are infinite combinations of C-factors in a network resulting the same head loss from source to test node. In addition, it was advised to take head measurements under a range of demand conditions in order to reduce compensating errors in pipe roughness values Distribution System Demands Estimation of nodal demands is a difficult stage of modeling which involves many uncertainties. For the sake of simplicity, nodal demands in a network model are summed up and extracted from junctions of the model. Actually, demands are extracted uniformly by the consumers on the distribution line as shown in Figure 2.2. Generally speaking, combining nodal demands into a junction does not change simulation results significantly. However, very long pipes and facilities consuming large amount of water such as factories, swimming pools should be taken into account. For such facilities, a separate junction can be introduced in the model (Walski et al., 2003). Figure 2.2 Distribution of Demands on Pipes 9

25 2.5.4 System Maps A system map is one of the basic sources of information of a distribution network. Configuration of the network, lengths and diameters of pipes, topographical elevations of junctions, locations of valves can be observed on these maps. However, system maps may contain errors and mismatches even if they are built in digital media. Junction details on the maps are very significant, thus a wrong pipe connection in a model may yield to a completely different result. So, modelers should be aware about possible system map errors. Here, as a remedy, mapping technicians and field staff of the water utilities should work in coordination and any change in the network should be reflected to model (Walski et al., 2003) Temporal Boundary Conditions In water distribution networks, flow and pressure values are variable with time. Thus, synchronization during measurements is important. That means, pressure measurements at the test nodes should be consistent with the corresponding flow and HGL measurements at the source nodes. Although SCADA has been employed, results obtained should be evaluated extensively for excessive oscillations. A sample flow measurement chart have been presented in Figure 2.3 (Walski et al., 2003). 10

26 11 Flow (m 3 /h) Time (h) Figure 2.3 Sample Flow Measurement 11

27 2.5.6 Pump Characteristic Curves Pumps are usually introduced to models with characteristic curves provided by the manufacturer. However, aging of pumps is a situation that may occur in every system. If a 20 year old pump is modeled with head discharge relationship of the manufactured condition, it would have a higher capacity than the actual case. To compensate this, pump capacity tests should be carried out and actual curves should be obtained; in other words pumps should also be calibrated (Walski et al., 2003). 2.6 Data Preparation Bhave (1988) pointed out data preparation in five items: skeletonization of network, determination of head at source nodes and supply at source nodes, estimation of consumption at demand nodes and pipe head loss coefficients Skeletonization of Network Bhave (1988) defined skeletonization as ignoring small diameter pipes or grouping and replacing by equivalent pipes in order to make the model manageable. If excessive number of pipes are removed in skeletonization, the model may poorly represent the network (Bhave, 1988). Eggener and Polkowski (1976) stated that skeletonized networks would be more accurate if all the small diameter pipes near source and large concentrated demands are included in the model. Jeppson (1982) proposed formulas for equivalent pipes for replacing a set of pipes and recommended lumping length, diameter and head loss coefficients into a single resistance factor. However, network solver software require length, diameter and head loss coefficients of pipes as input 12

28 variables. So, it would be beneficial to use length and diameter of largest pipe as it is and adjusting its head loss coefficient according to removed pipes (Bhave, 1988). In this study, micro level skeletonization has been applied and only consumer connections have been ignored Head at Source Nodes Determination of head at source nodes is relatively easy. HGL elevation in tanks can be determined by staff gauges installed in tanks, and head in the pumps can be measured by pressure gauges (Bhave, 1988) Supply at Source Nodes Average discharge at a tank can be determined by dividing volume of water leaving the tank to time passed. Rate of flow passing through pumps can be determined by using head discharge curves of pumps, if the curves are assumed to be accurate (Bhave, 1988). Nowadays, electromagnetic and ultrasonic flowmeters measure rate of flow in pipes accurately Consumption at Demand Nodes According to Bhave (1988), estimating consumption at demand nodes is rather difficult. Water consumption at a node depends on the area served by that node, type of consumption such as residential, public, or industrial and population density of the area. Since estimated nodal demands may not be accurate, they may need to be adjusted during calibration (Bhave, 1988). 13

29 2.6.5 Pipe Head Loss Coefficients According to Bhave (1988), the most difficult issue in calibration of networks is the selection of head loss coefficients (in this study, C-factor) for pipes. Pipe head loss coefficients can be estimated by using pipe age and material versus head loss coefficient charts. However, it should be noted that these coefficients are lumped parameters including other sources of head loss such as valves, fittings, service connections and pipe alignment deviations (Eggener and Polkowski, 1976). 2.7 Proposed Methods for Calibration There have been various techniques developed in order to calibrate network models in the literature. Walski et al. (2003) prepared a table summarizing calibration methods developed till the publish date of their book. A portion of the methods and more recent studies, their theoretical basis, and scopes have been presented below. Walski (1983) developed an iterative method to adjust both nodal demands and C coefficients. The method is based on HGL differences between source node and test node under low and high flow conditions. It was assumed that adjusted C value is representative for entire network pipes. This method may also change the rate of flow entering the network, even it is measured accurately (Chapter 3.2). Ormsbee and Wood (1986) approached calibration from a different point of view, by solving the problem explicitly. Apart from Walski (1983), in this 14

30 method hydraulic network equations had been solved in order to meet field measurements (pressure and flow). The non-linear energy equations have been linearized by Newton s Method. The calibrated network parameters of Ormsbee and Wood s (1986) Method are pipe roughness coefficients and predefined minor loss coefficients. The method is based on the assumption that demand loading and operation conditions are fairly accurate. This assumption is the weak point of the method, due to the difficulty in determining nodal demands accurately at every junction. Another method was developed by Bhave (1988) which depends on site measurements under different demand loadings, especially fire flow conditions. Similar to Walski s Mehtod (1983), Bhave s (1988) Method fits the model hydraulic grades according to source and test node HGLs obtained from site tests. The major difference of Bhave s (1988) Method from Walski s (1983) Method is the assumption that rate of the flow entering the network can be measured fairly accurate. Thus, nodal demands in one group of junctions are increased, while demands in the other junctions are decreased in the same amount. This method is also iterative like Walski s (1983) Merthod. However, when compared to automated methods, convergence rate is rather slow (Walski et al., 2003) (Chapter 3.3). After development of new optimization based computing techniques since early 90 s, new approaches to calibration have appeared in the literature. Genetic algorithm (GA) is one of these methods employed by researchers dealing with WDNs. Theory of genetic algorithm is based on the evolution theory of Darwin. This theory states that fittest individuals in a population have the highest probability of transferring their genes to next generations. 15

31 GA works in the same manner. A population is generated and members closest to the optimal solution are carried to next generations. There are crossover, mutation, cut and splice operators which constitute members with different codes from previous generation. Vitkovsky et al. (2000) employed GA for network calibration. Then, Wu et al. (2002) used the Darwin Calibrator module of WaterCAD software which bases GA for calibration of networks. Greco and Del Giudice (1999) proposed a new approach for calibration. The calibration problem have been tried to be solved by non-linear optimization with the objective to minimize the sum of the squares of the differences between predicted and calculated pipe roughness. Apart from other studies, Greco and Del Giudice (1999) have not minimized differences of pressure between observed and predicted measurements, but used pressure difference as a constraint. Calibration is also used for leak detection in networks. Borzi et al. (2005) had applied a GA based calibration in Parma, Italy for an extended period simulation with a duration of 24 hours. In this study, areas with large water loss had been detected. Wu and Sage (2006) employed calibration for detecting both location and magnitude of water loss based on GA optimization. After evaluating the available methods, Walski s (1983) and Bhave s (1988) Methods have been proposed to be applied in this study. The reason of selection of these methods is being relatively simple. Moreover, the network to be studied has been expected to have high level of uncertainty, and there 16

32 have been limited amount of data have been collected. Furthermore, size of the problem is relatively small, so that complex methods are not necessary. As stated by Speight and Khanal (2009), simpler methods are more common in recent calibration studies carried out by water utilities. 17

33 CHAPTER 3 3. THEORETICAL CONSIDERATIONS 3.1 General In this study, calibration methods proposed by Walski (1983) and Bhave (1988) have been employed. Both of the methods approach the problem on a deterministic way. In both methods, C-factors of pipes and nodal demands are adjusted until hydraulic grade levels in site observations and model match; both Walski s (1983) and Bhave s (1988) Methods are iterative. Several assumptions have been done for the sake of simplicity. Measurement chambers have been treated as fixed grade nodes (source node) and modelled as reservoirs. Elevations of pipe centre level in the chamber have been summed up with observed pressure in terms of meters. So, that hydraulic grade level at each chamber have been determined. During field tests, pressure readings fluctuated until system was stabilized. After the stabilization, magnitude of fluctuations reduced considerably. Average of readings of stabilized network were used during analysis. It was also assumed that pressure drop in points close to hydrants during fire flow would be the same with the pressure drop at the exact location of fire hydrant. By means of this assumption, pressure measurements could have 18

34 been done at the garden taps of the houses close to the test nodes. On the other hand, while measuring pressure on fire hydrants, minor losses increase significantly because of very high velocity of flow in the hydrant and auxiliary instruments. Fire hoses generally bend up and disturb the flow of water considerably. 3.2 Walski s Method (1983) Walski (1983) developed a method for calibrating network models which adjusts both pipe roughness coefficients and nodal demands of the network simultaneously in order to fit the model to site adjustments Development of the Method Hydraulic grade line levels at a test node (fire hydrant) are h 1 and h 2 corresponding to low flow condition Q and high flow condition Q + Q f, respectively. Q f, denotes the flow extracted from the hydrant during test. H is the hydraulic grade line level near a constant head node. Unknowns of the problem are total water consumption Q corresponding to h 1 and pipe roughness coefficient C-factor for all pipes. In order to develop a simple method, Walski (1983) assumed a single equivalent pipe from source node to test node. The head loss between source node and test node at low and high flow was expressed as: S H1 h1 K1 C (3.1a) 19

35 S Q f H2 h2 K2 C (3.1b) Here; Q f = difference between low flow and high flow (l/s), H 1 = hydraulic grade line level at the source node at low flow (m), H 2 = hydraulic grade line level at the source node at high flow (m), h 1 = hydraulic grade line level at the test node at low flow (m), h 2 = hydraulic grade line level at the test node at high flow (m), K 1 = K for equivalent pipe at low flow, K 2 = K for equivalent pipe at high flow, S = total water usage at the nodes significantly affecting hydrant test (l/s). Unknowns in the Eqs. 3.1a and 3.1b are K 1, K 2, S, and C. K 1 and K 2 depend on the lengths and diameters of the pipes. For a tank or a pressure reducing valve hydraulic grade levels for low and high flows may be equal as H 1 = H 2. Here, K 1 and K 2 can be estimated by initial estimations of S and C (noted as S e and C e ). After assigning initial values in the model, the modeler can predict the values of h 3 and h 4 for low and high flow, respectively. 20

36 K H h C e Se K H h 1.85 C e Se Q f...(3.2a) (3.2b) In which, h 3 = model prediction of h 1 for S e and C e (m), h 4 = model prediction of h 2 for S e and C e (m). Inserting the values of K 1 and K 2 into Eqs. 3.1 and solving for S and C, resultant equations becomes: S Qf ASe...(3.3a) b Qf 1 1 a Se QC f e C b( S Q ) as e f e BC...(3.3b). e Where, H a H h h (3.3c) and H b H h h (3.3d). 21

37 As a result, and Qf A b ( S Q ) S a B Qf b ( S Q ) as e f e e f e...(3.3e)...(3.3f). Eqs. 3.3 can be used to adjust C and S through calibration. Walski (1983) stated that a and b give information about the source and magnitude of error in initial estimations and also prepared the following table. Table 3.1 Interpretation of a and b (Walski, 1983) Value a b <1 Too much head loss predicted Too much head loss predicted at at low flow high flow =1 Head loss correct at low flow Head loss correct at high flow >1 Too little head loss predicted at low flow Too little head loss predicted at high flow Finally adjustments are done by using A and B such as: S i AS, i = 1,2,..,.m...(3.4) ei C j BC, j = 1,2,...,m...(3.5) ej Walski (1983) recommended a 9-step procedure for the technique: 1. Prepare the model as accurate as possible. 2. Assume initial values for C and S and run the model. 22

38 3. Obtain the values of H 1, H 2, h 1, h 2, and S f from site tests. 4. If the results obtained from the model with initial estimates are close enough to values taken from site observations the system can be said to be calibrated and no adjustment is necessary. 5. Calculate a and b. 6. Calculate C and S. 7. Run the model with corrected values. 8. If the results are close enough to observations calibration is complete, stop iterations. 9. Turn back to Step 5, do the same steps. If desired values are still not reached, turn back to Step 3 and do the site tests again Calibration of an Example System The example network has been shown in Figure 3.1. This network is an imaginary network. All properties are known including nodal demands and C- factors. HGL results obtained from the model with known parameters are treated as site measurements. So, it has been checked that whether the method gives accurate results close to actual values. Pipe properties and estimated C-factor values for the first iteration can be seen in the Table 3.2 and estimated nodal demands can be seen in Table 3.3. In the field tests during low flow conditions, hydraulic grade level during the test node (J-10) has been measured as m. In the same node, hydraulic grade level has been measured as 9.67 m with 20 l/s water extraction from 23

39 the fire hydrant. In both low and high flow conditions water level in the reservoir has been measured as 45 m. Figure 3.1 Example System for Walski s (1983) Method 24

40 Table 3.2 Pipe Properties of the Example System Pipe Label Length (m) Estimated Hazen- Williams C Diameter (mm) P P P P P P P P P P P P P P Table 3.3 Estimated Nodal Demands for Example System Junction Label Demand (l/s) Junction Label Demand (l/s) J J J J J J J J J Predicted hydraulic grade levels at the test node in the first iteration with C = 120 for all pipes are m and m at low and high flow conditions, respectively. According to this information, a and b have been computed as: a

41 b A and B have been found as: 20 A (56 20) B (56 20) At the end of the first iteration, adjusted values of C and S have been found as: C adj = B C est = = 94.7 and, S adj = A S est = = l/s. For the second iteration, estimated values for C and S are 94.7 and 55.81, respectively. Following iterations have been summarized in the Table 3.4, below. At the end of two trials, the values of C converged to 95. The meaning of this result is assumed value (120) for the first iteration was quite high. Value of S did not change significantly. That is, estimated water consumption for junctions were close enough to actual case. In fact, C-factors of all pipes were 95 and total water consumption was 56 l/s. So that the method yielded to accurate results. 26

42 Table 3.4 Summary of Iterations of Walski s (1983) Method for the Example System ITERATION FLOW SOURCE HGL (m) OBSERVED TEST NODE HGL (m) PREDICTED C PREDICTED TEST NODE HGL (m) LOW HIGH LOW HIGH ITERATION S (l/s) F (l/s) a b A B ADJUSTED C Bhave s Method (1988) The method adjusts both C-factors and nodal demands. Major difference between this method and Walski s (1983) Method is the assumption that total water consumption can be measured accurately and it remains constant during adjustments. In addition, the method allows users to divide the network into zones in terms of roughness coefficients and nodal demands. So that the system may not be forced to have a single roughness coefficient. 27

43 3.3.1 Development of the Method The basic equations of flow are nodal flow continuity equations and loop head loss equations. Node flow continuity equation states that the algebraic sum of flows at nodes must be zero. Qi qj 0 for all j...(3.6) i incident on j Q i = flow in pipe incident on node j; q j = external flow as supply or demand at node j. According to head loss equation, algebraic sums of head losses in pipes in a loop must be zero. Li h 0 for all c...(3.7) i c In which h L = head loss in pipe i contained on loop c. Equation 3.7 can include minor head losses and the heads supplied by pumps in the loops (Ormsbee and Wood 1986). In practice, for head loss determination Hazen Williams (H W) formula is used: KLQ hl C D...(3.8). 28

44 K = constant depending on the units of the other terms in the H-W formula (10.67 for metric unit); L = length of pipe; Q = flow in pipe; C = Hazen-Williams roughness coefficient; D = diameter of pipe. The general form of head loss equation is known as: h L = RQ n...(3.9) R = overall resistant constant, n = exponent, (between 1.7 and 2.0). In the method proposed by Bhave (1988), it is assumed that inflow at the source node can be measured or estimated fairly accurately and therefore it is known and remains fixed during calibration. Since both nodal demands and head loss coefficients are adjusted, at least two additional conditions must be available. Necessary data can be provided by measuring heads at two demand nodes under a particular loading condition, or at a demand node under normal and fire flow conditions, or at a demand node under two different loading conditions (Bhave, 1988). Bhave (1988) illustrated an example model in Figure 3.2. In this figure, s is a source node and t 1 and t 2 are test nodes. The network has been divided into two zones, one for each test node, as shown in the Figure 3.2. ΔQ 1 and ΔQ 2 are demand adjustments for Zones 1 and 2, respectively. ΔQ 1 = -ΔQ 2 so that demand adjustment for the entire network is zero (Bhave, 1988). 29

45 Figure 3.2 An Illustrative Figure (Bhave, 1988) Considering a path from s to t 1 as shown by thick lines in Figure 3.2, and labeling the pipes on this path as 1,3,...,i,..., the following equation can be written: R 1 (Q 1p ) n + R 3 (Q 3p ) n R i (Q ip ) n +... = H s H t1p...(3.10). R 1, R 3,..., R i = overall resistance coefficients of pipes 1,3,...,i,...; Q 1p, Q 3p,..., Q ip,... = discharge in pipes 1,3,...,i,... for the estimated nodal demands and 30

46 pipe resistant constants; H s = head at source s; H t1p = predicted head at node t 1. Assuming the entire correction factor for Zone-1 as ΔQ 1, which is applied to pipe 1 on path s-t 1 in proportion to the discharge carried by a pipe; the adjustment for pipe i is ΔQ i = Q ip /ΔQ 1p. In addition, B is the global adjustment factor for pipe resistance constants for path s-t 1. n n n Q3 p Qip 1 1p p 1... i ip 1... s t1 1p 1p BR Q Q BR Q Q BR Q Q H H Q Q...(3.11) Expanding Eq. 3.11, neglecting higher order terms of ΔQ 1 and combining with Eq and simplifying the following equation yields to: nb Hs Ht1 p B Hs Ht1 p Q1 Hs Ht1...(3.12). Q1 p Since B 1, Bhave (1988) took B = 1 in Eq for simplicity for the second term. n Hs Ht1 p B Hs Ht1 p Q1 Hs Ht1...(3.13) Q1 p 31

47 Similarly, considering path s-t 2, and taking ΔQ 2 = - ΔQ 1 n Hs Ht 2 p B Hs Ht 2 p Q1 Hs Ht 2...(3.14) Q2 p in which Q 2 is the flow in the first pipe on path s-t 2. When Eqs and 3.14 are solved simultaneously, values of B and ΔQ 1 can be calculated. Then, adjusted C-factor is: C ia 1 Cip...(3.15) B Correction factor for each nodal demand can be computed according to the following equation: q ja q jp 1 Q z q...(3.16) jp j Nz in which q jp = predicted demand at node j; ΔQ z = total nodal flow adjustment for zone z; and N z = set of demand nodes in zone z. 32

48 Bhave (1988) proposed the following ten-step calibration procedure: 1. Preparation of the model data as accurate as possible, making the total outflow equal to the total inflow for the entire network. 2. Measuring the heads at the source node and at the test nodes for one or more loading conditions. Also measuring the fire flow if fire flow test are to be carried out. 3. Making the runs of the model for the predicted values for the selected conditions. 4. Obtaining the heads at the test nodes, determining the head losses from the source to the test nodes, and calculating the ratios of the head losses of the predicted to observed conditions. 5. If the ratios of observed and predicted HGL levels are acceptable, the calibration is complete. Otherwise, continue. 6. Determination of the number of additional equations available for calibration. It should be noted that, in a multisource network, as the heads and supplies at all source nodes are treated as known, the head at only one source node serves as a reference node and the head at each of the remaining source nodes provides additional equations. 7. Divide the network into zones of both C-factor and demand adjustments, and decide the number of B s and ΔQ s so that their sums exceeds the number of equations by one. This is because the one equation comes from the sum of ΔQ s are zero. Also following three items should be taken into account that all the paths: (1) together cover all the zones; (2) lie in the general direction of flow; and (3) contain pipes that carry majority of flow 33

49 towards the test nodes as seen from the runs of the model for predicted condition (step 3). The same principle can be used for selection of paths for multisource networks. This step is done only for the first iteration. 8. Framing appropriate adjustment equations for the selected paths solving and determination of the values of B s and ΔQ s. 9. Adjusting the pipe resistance coefficients and nodal demands. 10. Treating the adjusted values as predicted values and return to step Calibration of the Example System A calibration problem has been created with a similar approach in the example network in the Section Actually, all network parameters were known, and HGL values obtained from network analysis had been treated as site observations. Then it was tried to obtain the actual roughness coefficients by calibration. Forgetting the actual value of roughness coefficients, a C-factor had been assigned to entire network and Bhave s (1988) method was applied. The network, which can be seen in the Figure 3.3, has been divided into two sub networks starting from the source node (east and west parts). Thus, one test node has been specified for each part which are, J-4 and J-13. Fire flow extraction from each test node were 5 m 3 /min (83.33 l/s) during site tests. Pipe properties of the network and estimated nodal demands are shown in Tables 3.5 and 3.6, respectively. 34

50 Figure 3.3 Example System 35

51 Table 3.5 Pipe Properties of Example System Pipe Length Diameter Estimated Hazen- Pipe Length Diameter Estimated Hazen- (m) (mm) Williams C (m) (mm) Williams C Table 3.6 Estimated Nodal Demands for Example System Junction Demand (m 3 /min) Junction Demand (m 3 /min) J J J J J J J J J J J J J J Flow paths related to each test node have been selected as: J-4: Pipes J-13: Pipes

52 Hydraulic grade values observed in field observations are given in the Table 3.7, below. Water level in tank T-2 was measured as m during site tests. Table 3.7 Observed Hydraulic Grades in the Field Tests Observed HGL (m) Junction Low Flow High Flow J J Four equations are available from site observations. Thus, four adjustment coefficients have been proposed which are B 1, B 2, B 3, for roughness coefficient adjustments; and F for nodal demand corrections. Pipes included in each zone have been listed below: Equations according to test nodes, path selection and zoning have been written as: h h F B h h h for low flow, T 2 j 4, p 1 f 20,21,22 T 2 j 4, o Q h h F B h h h for high flow, T 2 j 4, p 1 f 20,21,22 T 2 j 4, o Q20 37

53 3, 4 12,19 T 2 j 13, p 2 f 3 f T 2 j 13, o Q h h F B h B h h h for low flow, 3, 4 12,19 T 2 j 13, p 2 f 3 f T 2 j 13, o Q h h F B h B h h h for high flow, Following equations have been generated after inserting the predicted values of head loss in pipes into the above equations for the first iteration: 4.31B 0.94 F 4.31, B F 49.90, B 6.03B 0.32 F 16.30, B 47.54B F Results of the abovementioned equations and following iterations have been listed in Table 3.8. Table 3.8 Summary of Results of Equations for Example System Iteration B 1 B 2 B 3 ΔF C 1,adj C 2,adj C 3,adj Since ΔF was very small, no corrections have been done in nodal demands. Final adjusted values of C 1, C 2 and C 3 have been found as 120, 140 and 109, 38

54 respectively. The method gave precise results. Actual values of C-factors were 120, 140, and 109 for Zones 1,2,and 3, respectively Application of the Method in the Case Study There is only one hydrant for each sub-zone. Thus, number of the equations reduces to 2 for each sub-zone. The method has been modified and simplified according to some assumptions. First of all, the nodal demands extracted from junctions are assumed to be constant during the site tests. This means that ΔQ becomes zero and regarding parts in the equations have been eliminated and reduced to the following form: B Hs Htip Hs Hti...(6.12) At the early stages of the study, two adjustment coefficients were proposed for C-factors because there were two measurements for two loading conditions. However, during the analysis it was observed that head losses during low flow and high flow conditions were not compatible with each other. This incompatibility was realized when a negative B obtained from head loss equations. An example of this situation has been given in below for Yayla the sub-zone. So, only the test results at high flow are used for the calibration of the sub-zones. Pipes belonging to each path and head losses have been shown in Table B7, in Appendix B. Adjustment zones for C-factor and the path for Yayla sub-zone have been shown in Figure

55 Figure 3.4 Adjustment Zones and Path for Yayla Calibration equations according to Data Set-1 have been shown below: 0.09B 0.02B B 4.42B B 1 and B 2 have been found as and -3.00, respectively. The same problem was faced while studying other zones. Thus, one loading condition and one C-factor adjustment coefficient have been used for entire sub-zone. 40

56 CHAPTER 4 4. FIELD WORKS For adequate calibation of the N8.3 Pressure Zone, mathematical model of the network has been established, necessary preparations for data collection have been conducted, and field tests were carried out. 4.1 Establishment of the Model Hydraulic model of N8.3 had already been built by ASKİ staff before calibration study. Lengths and diameters of pipes in the model have been assigned according to project drawings. Measured nodal demands have been distributed to junctions by using semi pipe length approach. In this approach, total demand of junctions are distributed according to ratio of total of half lengths of pipes connecting to a junction to total pipe length in the network. The mathematical model was provided by ASKİ. 4.2 Construction Works Since the network was in a poor situation before the calibration study, rehabilitation works were carried out in order to improve the reliability of the field tests. 41

57 4.2.1 Determination of Valve Locations While constructing networks, isolation valves are installed on pipes at the points deemed to be necessary. However, as years pass, valves are buried under asphalt cover because of careless works on the streets. Once a valve is covered, it is difficult to find it, because valve locations are not always clearly defined in drawings. Furthermore, staff of the water authorities can have no prediction about the status of lost valves. Such situations make that portion of the network unable to be managed. An example of covering network components with careless work is shown in Figure 4.1. Even the cover of a measurement chamber was covered by asphalt. Figure 4.1 Asphalt Covered Measurement Chamber Cover In N8.3 there were many lost valves. ASKİ found the places of valves by using special instruments scanning underground which are sensitive to metal. Then covers of those valves have been carried over ground. After this work the network became operable in terms of valves. In Figure 4.2 cover of a valve can be seen. 42

58 Figure 4.2 A Valve Cover Installation of Fire Hydrants Fire hydrants are elements that are used for fire extinguishing. Hydrants also have important role in network management like flushing and draining the networks. In this study hydrants are one of the most important instruments because large amount of flow could have only been extracted from hydrants. Generally, number of the hydrants on streets are less than the necessary number. N8.3 Pressure Zone was also in a similar situation. In addition, most of the hydrants were underground type which are not practical to use. For the experiments, at least one surface type hydrant have been installed to each sub-zone by ASKİ. A surface type fire hydrant is shown in Figure

59 Figure 4.3 Fire Hydrant Construction of Measurement Chambers In this study, measurement chambers are source nodes with known HGL. They are rooms constructed under roads where the main pipes entering sub-zones can be accessed. Entire flow entering the sub-zones passes through the pipe in measurement chamber. Measurements regarding source nodes are carried out in these chambers. Flowmeters are mounted on the pipe. For pressure measurements, there is a sleeve on pipe for mounting pressure gauges. Inside view of a measurement chamber is shown in Figure

60 Figure 4.4 A Measurement Chamber 4.3 Isolation of Sub-Zones At the early stages of the study, pressure measurements were done at all hydrants simultaneously. After the test it was observed that drop in pressure during the test was not sufficient for analysis. In addition, synchronization between experimenters measuring flow and pressure at hydrants became a problem. Another difficulty of dealing with the whole network is the number of necessary staff for the site test. At least two people are required per one hydrant. So, for N8.3, nearly 15 attendants would be required. Furthermore, the most significant advantage of isolation of sub-zones is the reduction in the 45

61 complexity of the problem. Each sub-zone is treated as a separate network. So, classical methods became applicable. By means of the works mentioned in Section 4.2, N8.3 have been prepared for isolation. The isolated sub-zones are Yayla, North Sancaktepe, South Sancaktepe, Şehit Kubilay, Upper Çiğdemtepe, Lower Çiğdemtepe. Apparent valves on the boundaries of the sub-zones have been closed, so no flow between sub-zones is permitted. However, it should be noted that there may also be missing valves that could not be found and brought out. 4.4 Utilization of GIS Geographic Information System (GIS) is a powerful tool for modeling distribution networks. All of the components of the system such as pipes, valves, reservoirs can be visualized in digital media. Another useful feature of GIS programs is their common databases with other software. By this feature, operators can transfer data to other programs. For example, elevations of junctions in the network can be transferred to WaterCAD as the elevation property of junctions. Network model of N8.3 had been built by means of GIS. Topographic map had been combined with cadastral information of the zone. After that, pipes and other elements were drawn according to existing drawings. Finally, digital drawing of the network was transferred to WaterCAD. 46

62 4.5 Site Tests For the study, three types of data were collected: (i) topographic position of source and test nodes, (ii)pressure at source and test nodes, and (iii) the flow entering the network Topographic Position Measurements Calibration methods have been utilized in this study use hydraulic grade level between source and test nodes for adjustments. In order to obtain hydraulic grade level of a node, both pressure and topographical elevation at that point should be known. Since head loss in the network during normal flow conditions is very low, accurate measurement of elevations of both source and test nodes is important. That means, Z-coordinates should have been measured from pipe center level at source nodes, and from tap level for test nodes as accurate as possible. Because of this fact, the most accurate way of measuring topographic data have been proposed as GPS (Global Positioning System). GPS device available at ASKİ could measure Z-coordinate with centimeter accuracy. In Figure 4.5, a photo captured while the technician was measuring coordinates of a garden tap can be seen. 47

63 Figure 4.5 GPS Measurement Measurement of Coordinates of Measurement Chambers As stated before, topographic elevations should have been measured from pipe center level. However, GPS device can only measure ground elevation since it cannot be inserted in the measurement chamber. So, for determining exact elevation of pipe center level, distance between ground and center level has been measured by a tape measure and subtracted from ground elevation Measurement of Coordinates of Test Node Taps Pressure heads have been measured at a close garden tap near the fire hydrants as discussed in the Chapter 3. X, Y, and Z coordinates obtained from measurements have been shown in Table

64 Table 4.1 Coordinates of Test Nodes and Measurement Chambers Node Coordinate X (m) Y (m) Z (m) Yayla Test Node 485, ,428, , Yayla Measurement Chamber 484, ,429, , N. Sancaktepe Test Node 483, ,429, , N. Sancaktepe Measurement 483, ,429, , Chamber S. Sancaktepe Test Node 484, ,428, , S. Sancaktepe Measurement Chamber 483, ,429, , Ş. Kubilay Test Node 483, ,429, , Ş. Kubilay Measurement Chamber 483, ,429, , U. Çiğdemtepe Test Node 482, ,429, , U.Çiğdemtepe Measurement Chamber 482, ,429, , L. Çiğdemtepe Test Node 482, ,429, , L.Çiğdemtepe Measurement Chamber 482, ,429, , Pressure Measurements The Setup The setup used in the experiments was prepared by ASKİ staff. Two hoses connected to hydrant are coincided with a pant. Then, a hose leaving the pant is connected to a strainer which provides weight to prevent warping of the setup under the force of flow. Finally, water is discharged to the nearest sewerage manhole by a steel pipe connected to strainer. Pictures of the setup can be seen in Figures 4.6 and

65 Figure 4.6 Fire Hose Setup Figure 4.7 Strainer and Discharge Pipe Measurements Two field tests have been carried out for pressure measurements. The first test was done by using analogue manometers. After the test, inaccuracies 50

66 have been observed in the test results. For example, HGL calculated in the measurement chamber of North Sancaktepe was lower than test node HGL. Such a case is an indicator of error in measurement. It was predicted that manometer inaccuracy is the reason of this error. So, digital manometers were provided by ASKİ and a second site test was carried out. A picture of digital manometer taken during test have been shown in Figure 4.8. Results obtained from the second test have been used for analysis. Figure 4.8 Digital Manometer Pressure values read on the screen of manometer are in terms of bars. In order to convert the unit to meters of water column, the measured value have been multiplied by a conversion factor which is An important issue during site tests was waiting after opening hydrants until the network had been balanced. Here, balanced network stands for no significant change 51

67 occurs at pressure and discharge values read during fire flow. In order to balance the network, pressure measurements lasted for 3 5 minutes; and the average value of observations was taken as final measurement for each test node. Pressure measurements obtained in the site tests are shown in Table 4.2. Table 4.2 Pressure Measurements Node High Flow Pressure Low Flow bar m water column bar m water column Yayla Test Node Yayla Measurement Chamber N. Sancaktepe Test Node N. Sancaktepe Measurement Chamber S. Sancaktepe Test Node S. Sancaktepe Measurement Chamber Ş. Kubilay Test Node Ş. Kubilay Measurement Chamber U. Çiğdemtepe Test Node U. Çiğdemtepe Measurement Chamber L. Çiğdemtepe Test Node L. Çiğdemtepe Measurement Chamber Discharge Measurements Discharges were measured by ultrasonic flowmeters mounted on inlet pipes passing through measurement chamber. In Figure 4.9, the part of device used for screening and adjusting settings is shown. Input parameters for 52

68 measurement are pipe material, diameter and wall thickness of the pipe. Fire flow extracted have been calculated by subtracting low flow discharge from high flow discharge. Unit of the measurements was m 3 /min and measurements have been converted to l/s. Discharge measurements can be seen in Table 4.3. Figure 4.9 Ultrasonic Flowmeter 53

69 Table 4.3 Discharge Measurements Node Low Flow High Flow Hydrant Flow m 3 /min l/s m 3 /min l/s l/s Yayla Measurement Chamber N. Sancaktepe Measurement Chamber S. Sancaktepe Measurement Chamber Ş. Kubilay Measurement Chamber U. Çiğdemtepe Measurement Chamber L. Çiğdemtepe Measurement Chamber The measurements have been summarized in Table 4.4. After the preliminary studies carried out by using Data Set-1, another field test has been carried out and results of this test have been shown in Table

70 55 Table 4.4 Summary of the Measurements (Set-1) Yayla Test Node Elevation (m) Test Node Pressure (m) Test Node Hydraulic Grade Line Level (m) Inlet Elevation (m) Inlet Pressure (m) Inlet Hydraulic Grade Line Level (m) Inlet Discharge (l/s) Hydrant Flow (l/s) Low Flow High Flow Test Node Elevation (m) Test Node Pressure (m) Test Node Hydraulic Grade Line Level (m) North Sancaktepe Inlet Elevation (m) Inlet Pressure (m) Inlet Hydraulic Grade Line Level (m) Inlet Discharge (l/s) Hydrant Flow (l/s) Low Flow High Flow Test Node Elevation (m) Test Node Pressure (m) Test Node Hydraulic Grade Line Level (m) South Sancaktepe Inlet Elevation (m) 55 Inlet Pressure (m) Inlet Hydraulic Grade Line Level (m) Inlet Discharge (l/s) Low Flow High Flow Hydrant Flow (l/s)

71 56 Table 4.4 Summary of the Measurements (Set-1) Continued Şehit Kubilay Test Node Elevation (m) Test Node Pressure (m) Test Node Hydraulic Grade Line Level (m) Inlet Elevation (m) Inlet Pressure (m) Inlet Hydraulic Grade Line Level (m) Inlet Discharge (l/s) Hydrant Flow (l/s) Low Flow High Flow Test Node Elevation (m) Test Node Pressure (m) Test Node Hydraulic Grade Line Level (m) Upper Çiğdemtepe Inlet Elevation (m) Inlet Pressure (m) Inlet Hydraulic Grade Line Level (m) Inlet Discharge (l/s) Hydrant Flow (l/s) Low Flow High Flow Test Node Elevation (m) Test Node Pressure (m) Test Node Hydraulic Grade Line Level (m) Lower Çiğdemtepe Inlet Elevation (m) 56 Inlet Pressure (m) Inlet Hydraulic Grade Line Level (m) Inlet Discharge (l/s) Low Flow High Flow Hydrant Flow (l/s)

72 57 Table 4.5 Summary of the Measurements (Set-2) Yayla Test Node Elevation (m) Test Node Pressure (m) Test Node Hydraulic Grade Line Level (m) Inlet Elevation (m) Inlet Pressure (m) Inlet Hydraulic Grade Line Level (m) Inlet Discharge (l/s) Hydrant Flow (l/s) High Flow Mod. Flow Test Node Elevation (m) Test Node Pressure (m) Test Node Hydraulic Grade Line Level (m) North Sancaktepe Inlet Elevation (m) Inlet Pressure (m) Inlet Hydraulic Grade Line Level (m) Inlet Discharge (l/s) Hydrant Flow (l/s) High Flow Mod. Flow Test Node Elevation (m) Test Node Pressure (m) Test Node Hydraulic Grade Line Level (m) South Sancaktepe Inlet Elevation (m) 57 Inlet Pressure (m) Inlet Hydraulic Grade Line Level (m) Inlet Discharge (l/s) High Flow Mod. Flow Hydrant Flow (l/s)

73 58 Table 4.5 Summary of the Measurements (Set-2) Continued Şehit Kubilay Test Node Elevation (m) Test Node Pressure (m) Test Node Hydraulic Grade Line Level (m) Inlet Elevation (m) Inlet Pressure (m) Inlet Hydraulic Grade Line Level (m) Inlet Discharge (l/s) Hydrant Flow (l/s) High Flow Mod. Flow Test Node Elevation (m) Test Node Pressure (m) Test Node Hydraulic Grade Line Level (m) Upper Çiğdemtepe Inlet Elevation (m) Inlet Pressure (m) Inlet Hydraulic Grade Line Level (m) Inlet Discharge (l/s) Hydrant Flow (l/s) High Flow Mod. Flow Test Node Elevation (m) Test Node Pressure (m) Test Node Hydraulic Grade Line Level (m) Lower Çiğdemtepe Inlet Elevation (m) 58 Inlet Pressure (m) Inlet Hydraulic Grade Line Level (m) Inlet Discharge (l/s) High Flow Mod. Flow Hydrant Flow (l/s)

74 CHAPTER 5 5. CASE STUDY: MODEL CALIBRATION OF N8.3 PRESSURE ZONE, ANKARA 5.1 General Information About N8.3 Pressure Zone N8.3 pressure zone is located in Keçiören and Yenimahalle districts, in the northern part of City of Ankara. A satellite view of the zone can be seen in Figure 5.1. Schematic illustration of the sub-zones developed in GIS media of N8.3 can be seen in Figure 5.2. Green lines in the drawing imply network pipes, blues lines represent main transmission lines, and black dots represent isolation valves in the network. Geographically, the zone can be defined as hilly. Minimum and maximum elevations of the zone are 1075 m and 1120 m above sea level, respectively. Water usage characteristic of the zone can generally be described as residential. There are no industrial facilities in the zone; furthermore, there exist schools and green areas. Population density of the zone differs from region to region. In early years, many of the houses were single floored. Till then, some of these houses have been reconstructed and multi-storey residential buildings have been built. Reconstructed regions can be distinguished from single floored houses in Figure 5.1. These reconstruction activities will cause an increase in the population of the zone, so in water consumption. Economic level of the people living in the zone can be defined as middle-low and low. Water consumption reaches peak value about p.m. There is no exact data available about population of the zone. 59

75 M.C.: Measurement Chamber T.N.: Test Node Figure 5.1 Satellite View of N8.3 (Google) 60

76 Distribution Pipe Transmission Line Valve LEGEND North Sancaktepe Lower Çiğdemtepe T-53 Reservoir P-23 Pumping Station Şehit Kubilay Yayla South Sancaktepe Upper Çiğdemtepe Figure 5.2 Sub-Zones of N8.3 61

A UNIFIED APPROACH IN GPS ACCURACY DETERMINATION STUDIES

A UNIFIED APPROACH IN GPS ACCURACY DETERMINATION STUDIES A UNIFIED APPROACH IN GPS ACCURACY DETERMINATION STUDIES by Didem Öztürk B.S., Geodesy and Photogrammetry Department Yildiz Technical University, 2005 Submitted to the Kandilli Observatory and Earthquake

Detaylı

Unlike analytical solutions, numerical methods have an error range. In addition to this

Unlike analytical solutions, numerical methods have an error range. In addition to this ERROR Unlike analytical solutions, numerical methods have an error range. In addition to this input data may have errors. There are 5 basis source of error: The Source of Error 1. Measuring Errors Data

Detaylı

WEEK 11 CME323 NUMERIC ANALYSIS. Lect. Yasin ORTAKCI.

WEEK 11 CME323 NUMERIC ANALYSIS. Lect. Yasin ORTAKCI. WEEK 11 CME323 NUMERIC ANALYSIS Lect. Yasin ORTAKCI yasinortakci@karabuk.edu.tr 2 INTERPOLATION Introduction A census of the population of the United States is taken every 10 years. The following table

Detaylı

4. HAFTA BLM323 SAYISAL ANALİZ. Okt. Yasin ORTAKCI.

4. HAFTA BLM323 SAYISAL ANALİZ. Okt. Yasin ORTAKCI. 4. HAFTA BLM33 SAYISAL ANALİZ Okt. Yasin ORTAKCI yasinortakci@karabuk.edu.tr Karabük Üniversitesi Uzaktan Eğitim Uygulama ve Araştırma Merkezi BLM33 NONLINEAR EQUATION SYSTEM Two or more degree polinomial

Detaylı

WEEK 4 BLM323 NUMERIC ANALYSIS. Okt. Yasin ORTAKCI.

WEEK 4 BLM323 NUMERIC ANALYSIS. Okt. Yasin ORTAKCI. WEEK 4 BLM33 NUMERIC ANALYSIS Okt. Yasin ORTAKCI yasinortakci@karabuk.edu.tr Karabük Üniversitesi Uzaktan Eğitim Uygulama ve Araştırma Merkezi BLM33 NONLINEAR EQUATION SYSTEM Two or more degree polinomial

Detaylı

Ege Üniversitesi Elektrik Elektronik Mühendisliği Bölümü Kontrol Sistemleri II Dersi Grup Adı: Sıvı Seviye Kontrol Deneyi.../..

Ege Üniversitesi Elektrik Elektronik Mühendisliği Bölümü Kontrol Sistemleri II Dersi Grup Adı: Sıvı Seviye Kontrol Deneyi.../.. Ege Üniversitesi Elektrik Elektronik Mühendisliği Bölümü Kontrol Sistemleri II Dersi Grup Adı: Sıvı Seviye Kontrol Deneyi.../../2015 KP Pompa akış sabiti 3.3 cm3/s/v DO1 Çıkış-1 in ağız çapı 0.635 cm DO2

Detaylı

First Stage of an Automated Content-Based Citation Analysis Study: Detection of Citation Sentences

First Stage of an Automated Content-Based Citation Analysis Study: Detection of Citation Sentences First Stage of an Automated Content-Based Citation Analysis Study: Detection of Citation Sentences Zehra Taşkın, Umut Al & Umut Sezen {ztaskin, umutal, u.sezen}@hacettepe.edu.tr - 1 Plan Need for content-based

Detaylı

Yüz Tanımaya Dayalı Uygulamalar. (Özet)

Yüz Tanımaya Dayalı Uygulamalar. (Özet) 4 Yüz Tanımaya Dayalı Uygulamalar (Özet) Günümüzde, teknolojinin gelişmesi ile yüz tanımaya dayalı bir çok yöntem artık uygulama alanı bulabilmekte ve gittikçe de önem kazanmaktadır. Bir çok farklı uygulama

Detaylı

THE DESIGN AND USE OF CONTINUOUS GNSS REFERENCE NETWORKS. by Özgür Avcı B.S., Istanbul Technical University, 2003

THE DESIGN AND USE OF CONTINUOUS GNSS REFERENCE NETWORKS. by Özgür Avcı B.S., Istanbul Technical University, 2003 THE DESIGN AND USE OF CONTINUOUS GNSS REFERENCE NETWORKS by Özgür Avcı B.S., Istanbul Technical University, 2003 Submitted to the Kandilli Observatory and Earthquake Research Institute in partial fulfillment

Detaylı

12. HAFTA BLM323 SAYISAL ANALİZ. Okt. Yasin ORTAKCI. yasinortakci@karabuk.edu.tr

12. HAFTA BLM323 SAYISAL ANALİZ. Okt. Yasin ORTAKCI. yasinortakci@karabuk.edu.tr 1. HAFTA BLM33 SAYISAL ANALİZ Okt. Yasin ORTAKCI yasinortakci@karabuk.edu.tr Karabük Üniversitesi Uzaktan Eğitim Uygulama ve Araştırma Merkezi DIVIDED DIFFERENCE INTERPOLATION Forward Divided Differences

Detaylı

T.C. SÜLEYMAN DEMİREL ÜNİVERSİTESİ FEN BİLİMLERİ ENSTİTÜSÜ ISPARTA İLİ KİRAZ İHRACATININ ANALİZİ

T.C. SÜLEYMAN DEMİREL ÜNİVERSİTESİ FEN BİLİMLERİ ENSTİTÜSÜ ISPARTA İLİ KİRAZ İHRACATININ ANALİZİ T.C. SÜLEYMAN DEMİREL ÜNİVERSİTESİ FEN BİLİMLERİ ENSTİTÜSÜ ISPARTA İLİ KİRAZ İHRACATININ ANALİZİ Danışman Doç. Dr. Tufan BAL YÜKSEK LİSANS TEZİ TARIM EKONOMİSİ ANABİLİM DALI ISPARTA - 2016 2016 [] TEZ

Detaylı

ÇEVRESEL TEST HİZMETLERİ 2.ENVIRONMENTAL TESTS

ÇEVRESEL TEST HİZMETLERİ 2.ENVIRONMENTAL TESTS ÇEVRESEL TEST HİZMETLERİ 2.ENVIRONMENTAL TESTS Çevresel testler askeri ve sivil amaçlı kullanılan alt sistem ve sistemlerin ömür devirleri boyunca karşı karşıya kalabilecekleri doğal çevre şartlarına dirençlerini

Detaylı

THE ROLE OF GENDER AND LANGUAGE LEARNING STRATEGIES IN LEARNING ENGLISH

THE ROLE OF GENDER AND LANGUAGE LEARNING STRATEGIES IN LEARNING ENGLISH THE ROLE OF GENDER AND LANGUAGE LEARNING STRATEGIES IN LEARNING ENGLISH THESIS SUBMITTED TO THE GRADUATE SCHOOL OF SOCIAL SCIENCES OF MIDDLE EAST TECHNICAL UNIVERSITY BY OKTAY ASLAN IN PARTIAL FULFILLMENT

Detaylı

ATILIM UNIVERSITY Department of Computer Engineering

ATILIM UNIVERSITY Department of Computer Engineering ATILIM UNIVERSITY Department of Computer Engineering COMPE 350 Numerical Methods Fall, 2011 Instructor: Fügen Selbes Assistant: İsmail Onur Kaya Homework: 1 Due date: Nov 14, 2011 You are designing a spherical

Detaylı

1 I S L U Y G U L A M A L I İ K T İ S A T _ U Y G U L A M A ( 5 ) _ 3 0 K a s ı m

1 I S L U Y G U L A M A L I İ K T İ S A T _ U Y G U L A M A ( 5 ) _ 3 0 K a s ı m 1 I S L 8 0 5 U Y G U L A M A L I İ K T İ S A T _ U Y G U L A M A ( 5 ) _ 3 0 K a s ı m 2 0 1 2 CEVAPLAR 1. Tekelci bir firmanın sabit bir ortalama ve marjinal maliyet ( = =$5) ile ürettiğini ve =53 şeklinde

Detaylı

DETERMINATION OF VELOCITY FIELD AND STRAIN ACCUMULATION OF DENSIFICATION NETWORK IN MARMARA REGION

DETERMINATION OF VELOCITY FIELD AND STRAIN ACCUMULATION OF DENSIFICATION NETWORK IN MARMARA REGION DETERMINATION OF VELOCITY FIELD AND STRAIN ACCUMULATION OF DENSIFICATION NETWORK IN MARMARA REGION by İlke Deniz B.S. Geodesy and Photogrametry Engineering, in Yıldız Technical University, 2004 Submitted

Detaylı

CmpE 320 Spring 2008 Project #2 Evaluation Criteria

CmpE 320 Spring 2008 Project #2 Evaluation Criteria CmpE 320 Spring 2008 Project #2 Evaluation Criteria General The project was evaluated in terms of the following criteria: Correctness (55 points) See Correctness Evaluation below. Document (15 points)

Detaylı

Arýza Giderme. Troubleshooting

Arýza Giderme. Troubleshooting Arýza Giderme Sorun Olasý Nedenler Giriþ Gerilimi düþük hata mesajý Þebeke giriþ gerilimi alt seviyenin altýnda geliyor Þebeke giriþ gerilimi tehlikeli derecede Yüksek geliyor Regülatör kontrol kartý hatasý

Detaylı

MM103 E COMPUTER AIDED ENGINEERING DRAWING I

MM103 E COMPUTER AIDED ENGINEERING DRAWING I MM103 E COMPUTER AIDED ENGINEERING DRAWING I ORTHOGRAPHIC (MULTIVIEW) PROJECTION (EŞLENİK DİK İZDÜŞÜM) Weeks: 3-6 ORTHOGRAPHIC (MULTIVIEW) PROJECTION (EŞLENİK DİK İZDÜŞÜM) Projection: A view of an object

Detaylı

ACCURACY OF GPS PRECISE POINT POSITIONING (PPP)

ACCURACY OF GPS PRECISE POINT POSITIONING (PPP) i by Simge TEKİÇ B.S., Geodesy and Photogrammetry Engineering Yıldız Technical University, 2006 Submitted to the Kandilli Observatory and Earthquake Research Institute in partial fulfillment of the requirements

Detaylı

(1971-1985) ARASI KONUSUNU TÜRK TARİHİNDEN ALAN TİYATROLAR

(1971-1985) ARASI KONUSUNU TÜRK TARİHİNDEN ALAN TİYATROLAR ANABİLİM DALI ADI SOYADI DANIŞMANI TARİHİ :TÜRK DİLİ VE EDEBİYATI : Yasemin YABUZ : Yrd. Doç. Dr. Abdullah ŞENGÜL : 16.06.2003 (1971-1985) ARASI KONUSUNU TÜRK TARİHİNDEN ALAN TİYATROLAR Kökeni Antik Yunan

Detaylı

Atıksu Arıtma Tesislerinde Hava Dağıtımının Optimize Edilmesi ve Enerji Tasarrufu

Atıksu Arıtma Tesislerinde Hava Dağıtımının Optimize Edilmesi ve Enerji Tasarrufu Optimization of Air Distribution in Waste Water Treatment Plants to Save Energy Atıksu Arıtma Tesislerinde Hava Dağıtımının Optimize Edilmesi ve Enerji Tasarrufu Jan Talkenberger, Binder Group, Ulm, Germany

Detaylı

YARASA VE ÇİFTLİK GÜBRESİNİN BAZI TOPRAK ÖZELLİKLERİ ve BUĞDAY BİTKİSİNİN VERİM PARAMETRELERİ ÜZERİNE ETKİSİ

YARASA VE ÇİFTLİK GÜBRESİNİN BAZI TOPRAK ÖZELLİKLERİ ve BUĞDAY BİTKİSİNİN VERİM PARAMETRELERİ ÜZERİNE ETKİSİ ATATÜRK ÜNİVERSİTESİ FEN BİLİMLERİ ENSTİTÜSÜ DOKTORA TEZİ YARASA VE ÇİFTLİK GÜBRESİNİN BAZI TOPRAK ÖZELLİKLERİ ve BUĞDAY BİTKİSİNİN VERİM PARAMETRELERİ ÜZERİNE ETKİSİ TARIMSAL YAPILAR VE SULAMA ANABİLİM

Detaylı

AN ASSESSMENT OF THE DYNAMIC PROPERTIES OF ADAPAZARI SOILS BY CYCLIC DIRECT SIMPLE SHEAR TESTS

AN ASSESSMENT OF THE DYNAMIC PROPERTIES OF ADAPAZARI SOILS BY CYCLIC DIRECT SIMPLE SHEAR TESTS AN ASSESSMENT OF THE DYNAMIC PROPERTIES OF ADAPAZARI SOILS BY CYCLIC DIRECT SIMPLE SHEAR TESTS A THESIS SUBMITTED TO THE GRADUATE SCHOOL OF NATURAL AND APPLIED SCIENCES OF MIDDLE EAST TECHNICAL UNIVERSITY

Detaylı

T.C. Hitit Üniversitesi. Sosyal Bilimler Enstitüsü. İşletme Anabilim Dalı

T.C. Hitit Üniversitesi. Sosyal Bilimler Enstitüsü. İşletme Anabilim Dalı T.C. Hitit Üniversitesi Sosyal Bilimler Enstitüsü İşletme Anabilim Dalı X, Y, Z KUŞAĞI TÜKETİCİLERİNİN YENİDEN SATIN ALMA KARARI ÜZERİNDE ALGILANAN MARKA DENKLİĞİ ÖĞELERİNİN ETKİ DÜZEYİ FARKLILIKLARININ

Detaylı

24kV,630A Outdoor Switch Disconnector with Arc Quenching Chamber (ELBI) IEC IEC IEC 60129

24kV,630A Outdoor Switch Disconnector with Arc Quenching Chamber (ELBI) IEC IEC IEC 60129 24kV,630 Outdoor Switch Disconnector with rc Quenching Chamber (ELBI) IEC265-1 IEC 694 IEC 129 Type ELBI-HN (24kV,630,normal) Closed view Open view Type ELBI-HS (24kV,630,with fuse base) Closed view Open

Detaylı

AİLE İRŞAT VE REHBERLİK BÜROLARINDA YAPILAN DİNİ DANIŞMANLIK - ÇORUM ÖRNEĞİ -

AİLE İRŞAT VE REHBERLİK BÜROLARINDA YAPILAN DİNİ DANIŞMANLIK - ÇORUM ÖRNEĞİ - T.C. Hitit Üniversitesi Sosyal Bilimler Enstitüsü Felsefe ve Din Bilimleri Anabilim Dalı AİLE İRŞAT VE REHBERLİK BÜROLARINDA YAPILAN DİNİ DANIŞMANLIK - ÇORUM ÖRNEĞİ - Necla YILMAZ Yüksek Lisans Tezi Çorum

Detaylı

IDENTITY MANAGEMENT FOR EXTERNAL USERS

IDENTITY MANAGEMENT FOR EXTERNAL USERS 1/11 Sürüm Numarası Değişiklik Tarihi Değişikliği Yapan Erman Ulusoy Açıklama İlk Sürüm IDENTITY MANAGEMENT FOR EXTERNAL USERS You can connect EXTERNAL Identity Management System (IDM) with https://selfservice.tai.com.tr/

Detaylı

THE IMPACT OF AUTONOMOUS LEARNING ON GRADUATE STUDENTS PROFICIENCY LEVEL IN FOREIGN LANGUAGE LEARNING ABSTRACT

THE IMPACT OF AUTONOMOUS LEARNING ON GRADUATE STUDENTS PROFICIENCY LEVEL IN FOREIGN LANGUAGE LEARNING ABSTRACT THE IMPACT OF AUTONOMOUS LEARNING ON GRADUATE STUDENTS PROFICIENCY LEVEL IN FOREIGN LANGUAGE LEARNING ABSTRACT The purpose of the study is to investigate the impact of autonomous learning on graduate students

Detaylı

PRELIMINARY REPORT. 19/09/2012 KAHRAMANMARAŞ PAZARCIK EARTHQUAKE (SOUTHEAST TURKEY) Ml=5.1.

PRELIMINARY REPORT. 19/09/2012 KAHRAMANMARAŞ PAZARCIK EARTHQUAKE (SOUTHEAST TURKEY) Ml=5.1. PRELIMINARY REPORT 19/09/2012 KAHRAMANMARAŞ PAZARCIK EARTHQUAKE (SOUTHEAST TURKEY) Ml=5.1 www.deprem.gov.tr www.afad.gov.tr REPUBLIC OF TUKEY MANAGEMENT PRESIDENCY An earthquake with magnitude Ml=5.1 occurred

Detaylı

Yarışma Sınavı A ) 60 B ) 80 C ) 90 D ) 110 E ) 120. A ) 4(x + 2) B ) 2(x + 4) C ) 2 + ( x + 4) D ) 2 x + 4 E ) x + 4

Yarışma Sınavı A ) 60 B ) 80 C ) 90 D ) 110 E ) 120. A ) 4(x + 2) B ) 2(x + 4) C ) 2 + ( x + 4) D ) 2 x + 4 E ) x + 4 1 4 The price of a book is first raised by 20 TL, and then by another 30 TL. In both cases, the rate of increment is the same. What is the final price of the book? 60 80 90 110 120 2 3 5 Tim ate four more

Detaylı

HAZIRLAYANLAR: K. ALBAYRAK, E. CİĞEROĞLU, M. İ. GÖKLER

HAZIRLAYANLAR: K. ALBAYRAK, E. CİĞEROĞLU, M. İ. GÖKLER HAZIRLAYANLAR: K. ALBAYRAK, E. CİĞEROĞLU, M. İ. GÖKLER PROGRAM OUTCOME 13 Ability to Take Societal, Environmental and Economical Considerations into Account in Professional Activities Program outcome 13

Detaylı

İŞLETMELERDE KURUMSAL İMAJ VE OLUŞUMUNDAKİ ANA ETKENLER

İŞLETMELERDE KURUMSAL İMAJ VE OLUŞUMUNDAKİ ANA ETKENLER ANKARA ÜNİVERSİTESİ SOSYAL BİLİMLER ENSTİTÜSÜ HALKLA İLİŞKİLER VE TANITIM ANA BİLİM DALI İŞLETMELERDE KURUMSAL İMAJ VE OLUŞUMUNDAKİ ANA ETKENLER BİR ÖRNEK OLAY İNCELEMESİ: SHERATON ANKARA HOTEL & TOWERS

Detaylı

T.C. İSTANBUL AYDIN ÜNİVERSİTESİ SOSYAL BİLİMLER ENSTİTÜSÜ BİREYSEL DEĞERLER İLE GİRİŞİMCİLİK EĞİLİMİ İLİŞKİSİ: İSTANBUL İLİNDE BİR ARAŞTIRMA

T.C. İSTANBUL AYDIN ÜNİVERSİTESİ SOSYAL BİLİMLER ENSTİTÜSÜ BİREYSEL DEĞERLER İLE GİRİŞİMCİLİK EĞİLİMİ İLİŞKİSİ: İSTANBUL İLİNDE BİR ARAŞTIRMA T.C. İSTANBUL AYDIN ÜNİVERSİTESİ SOSYAL BİLİMLER ENSTİTÜSÜ BİREYSEL DEĞERLER İLE GİRİŞİMCİLİK EĞİLİMİ İLİŞKİSİ: İSTANBUL İLİNDE BİR ARAŞTIRMA DOKTORA TEZİ Cafer Şafak EYEL İşletme Ana Bilim Dalı İşletme

Detaylı

LEARNING AGREEMENT FOR TRAINEESHIPS

LEARNING AGREEMENT FOR TRAINEESHIPS İsminizi yazınız. LEARNING AGREEMENT FOR TRAINEESHIPS The Trainee Last name (s) Soyadınız First name (s) adınız Date of birth Doğum tarihiniz Nationality uyruğunuz Sex [M/F] cinsiyetiniz Academic year

Detaylı

Profiling the Urban Social Classes in Turkey: Economic Occupations, Political Orientations, Social Life-Styles, Moral Values

Profiling the Urban Social Classes in Turkey: Economic Occupations, Political Orientations, Social Life-Styles, Moral Values Profiling the Urban Social Classes in Turkey: Economic Occupations, Political Orientations, Social Life-Styles, Moral Values Presentation of the Basic Findings of a Public Opinion Survey Supported with

Detaylı

ISSN: Yıl /Year: 2017 Cilt(Sayı)/Vol.(Issue): 1(Özel) Sayfa/Page: Araştırma Makalesi Research Article. Özet.

ISSN: Yıl /Year: 2017 Cilt(Sayı)/Vol.(Issue): 1(Özel) Sayfa/Page: Araştırma Makalesi Research Article. Özet. VII. Bahçe Ürünlerinde Muhafaza ve Pazarlama Sempozyumu, 04-07 Ekim 206 ISSN: 248-0036 Yıl /Year: 207 Cilt(Sayı)/Vol.(Issue): (Özel) Sayfa/Page: 54-60 Araştırma Makalesi Research Article Suleyman Demirel

Detaylı

daha çok göz önünde bulundurulabilir. Öğrencilerin dile karşı daha olumlu bir tutum geliştirmeleri ve daha homojen gruplar ile dersler yürütülebilir.

daha çok göz önünde bulundurulabilir. Öğrencilerin dile karşı daha olumlu bir tutum geliştirmeleri ve daha homojen gruplar ile dersler yürütülebilir. ÖZET Üniversite Öğrencilerinin Yabancı Dil Seviyelerinin ve Yabancı Dil Eğitim Programına Karşı Tutumlarının İncelenmesi (Aksaray Üniversitesi Örneği) Çağan YILDIRAN Niğde Üniversitesi, Sosyal Bilimler

Detaylı

Eco 338 Economic Policy Week 4 Fiscal Policy- I. Prof. Dr. Murat Yulek Istanbul Ticaret University

Eco 338 Economic Policy Week 4 Fiscal Policy- I. Prof. Dr. Murat Yulek Istanbul Ticaret University Eco 338 Economic Policy Week 4 Fiscal Policy- I Prof. Dr. Murat Yulek Istanbul Ticaret University Aggregate Demand Aggregate (domestic) demand (or domestic absorption) is the sum of consumption, investment

Detaylı

Dairesel grafik (veya dilimli pie chart circle graph diyagram, sektor grafiği) (İngilizce:"pie chart"), istatistik

Dairesel grafik (veya dilimli pie chart circle graph diyagram, sektor grafiği) (İngilizce:pie chart), istatistik DAİRESEL GRAFİK Dairesel grafik (veya dilimli diyagram, sektor grafiği) (İngilizce:"pie chart"), istatistik biliminde betimsel istatistik alanında kategorik (ya sırasal ölçekli ya da isimsel ölçekli) verileri

Detaylı

BVCD DÝKDÖRTGEN HAVA DAMPERÝ ( BVCD) RECTANGULAR VOLUME CONTROL DAMPER

BVCD DÝKDÖRTGEN HAVA DAMPERÝ ( BVCD) RECTANGULAR VOLUME CONTROL DAMPER DÝKDÖRTGEN HAVA DAMPERÝ ( ) RECTANGULAR VOLUME CONTROL DAMPER Dikdörtgen Hava Damperi Teknik Detaylarý Rectangular Volume Control Damper Technical Details : Malzeme: Ürün kasa ve kanatlarýnýn tamamý ekstrüzyon

Detaylı

BINDER. İstikrarlı Süreç Yönetimi İle Verimliliğin Sağlanması. Bir Örnek Araştırma

BINDER. İstikrarlı Süreç Yönetimi İle Verimliliğin Sağlanması. Bir Örnek Araştırma İstikrarlı Süreç Yönetimi İle Verimliliğin Sağlanması Bir Örnek Araştırma 1 BINDER @ TR GWP Day 2016 in Mersin BINDER Hakkında Hava Kontrolü İle İstikrarlı Havalandırma VACOMASS Jet Control Valve Örnek

Detaylı

Argumentative Essay Nasıl Yazılır?

Argumentative Essay Nasıl Yazılır? Argumentative Essay Nasıl Yazılır? Hüseyin Demirtaş Dersimiz: o Argumentative Essay o Format o Thesis o Örnek yazı Military service Outline Many countries have a professional army yet there is compulsory

Detaylı

Kamuran Özlem Sarnıç (Sanatta Yeterlik Tezi)

Kamuran Özlem Sarnıç (Sanatta Yeterlik Tezi) OPTİK YANILSAMA ve SERAMİK SANATINDA KULLANIMI-UYGULAMALARI Kamuran Özlem Sarnıç (Sanatta Yeterlik Tezi) Eskişehir, Ağustos 2011 OPTİK YANILSAMA ve SERAMİK SANATINDA KULLANIMI- UYGULAMALARI Kamuran Özlem

Detaylı

PCC 6505 PROFILE CUTTING LINE

PCC 6505 PROFILE CUTTING LINE PCC 6505 PROFILE CUTTING LINE 1.DESCRIPTION PCC 6505 is a servo controlled machine which is specifically designed for the serial cutting of any kind of PVC and aluminum s in the market. The machine is

Detaylı

İKİ KADEMELİ GAZ BRÜLÖRLERİ TWO STAGE GAS BURNERS

İKİ KADEMELİ GAZ BRÜLÖRLERİ TWO STAGE GAS BURNERS Lİ GAZ BRÜLÖRLERİ TWO STAGE GAS BURNERS Doğru seçimle başlamak Starting the right selection ÜRET GAZ BRÜLÖRLERİ 30 7500 kw TS EN 676 + A2 çerçevesinde CE 1312 sertifikasyonu ile üretilen üflemeli tip Üret

Detaylı

BAYAN DİN GÖREVLİSİNİN İMAJI VE MESLEĞİNİ TEMSİL GÜCÜ -Çorum Örneği-

BAYAN DİN GÖREVLİSİNİN İMAJI VE MESLEĞİNİ TEMSİL GÜCÜ -Çorum Örneği- T.C. Hitit Üniversitesi Sosyal Bilimler Enstitüsü Felsefe ve Din Bilimleri Anabilim Dalı BAYAN DİN GÖREVLİSİNİN İMAJI VE MESLEĞİNİ TEMSİL GÜCÜ -Çorum Örneği- Lütfiye HACIİSMAİLOĞLU Yüksek Lisans Tezi Çorum

Detaylı

LANDE DYNAcenter Server Cabinet W600 X D1000 MECHANICAL TESTS REPORT

LANDE DYNAcenter Server Cabinet W600 X D1000 MECHANICAL TESTS REPORT 2014 TÜV SÜD TÜRKİYE REPORT NO: TGK-14-P-10236-1 JOB NO: 14-P-10236 12.10.2014 LANDE DYNAcenter Server Cabinet W600 X D1000 MECHANICAL TESTS REPORT INDEX INTRODUCTION... 5 2 MECHANICAL TESTS... 6 2.1 Static

Detaylı

ÖNEMLİ PREPOSİTİONAL PHRASES

ÖNEMLİ PREPOSİTİONAL PHRASES ÖNEMLİ PREPOSİTİONAL PHRASES Bu liste YDS için Önemli özellikle seçilmiş prepositional phrase leri içerir. 74 adet Toplam 74 adet İngilizce Türkçe Tür 1. with the help -ın yardımıyla with the aid -ın yardımıyla

Detaylı

KANSER HASTALARINDA ANKSİYETE VE DEPRESYON BELİRTİLERİNİN DEĞERLENDİRİLMESİ UZMANLIK TEZİ. Dr. Levent ŞAHİN

KANSER HASTALARINDA ANKSİYETE VE DEPRESYON BELİRTİLERİNİN DEĞERLENDİRİLMESİ UZMANLIK TEZİ. Dr. Levent ŞAHİN T.C. SAĞLIK BAKANLIĞI İZMİR KATİP ÇELEBİ ÜNİVERSİTESİ ATATÜRK EĞİTİM VE ARAŞTIRMA HASTANESİ AİLE HEKİMLİĞİ KLİNİĞİ KANSER HASTALARINDA ANKSİYETE VE DEPRESYON BELİRTİLERİNİN DEĞERLENDİRİLMESİ UZMANLIK TEZİ

Detaylı

Turkish Vessel Monitoring System. Turkish VMS

Turkish Vessel Monitoring System. Turkish VMS Turkish Vessel Monitoring System BSGM Balıkçılık ve Su Ürünleri Genel Balıkçılık Müdürlüğü ve Su Ürünleri Genel Müdürlüğü İstatistik ve Bilgi Sistemleri İstatistik Daire Başkanlığı ve Bilgi Sistemleri

Detaylı

ÖZET OTOMATİK KÖKLENDİRME SİSTEMİNDE ORTAM NEMİNİN SENSÖRLERLE HASSAS KONTROLÜ. Murat ÇAĞLAR

ÖZET OTOMATİK KÖKLENDİRME SİSTEMİNDE ORTAM NEMİNİN SENSÖRLERLE HASSAS KONTROLÜ. Murat ÇAĞLAR vii ÖZET OTOMATİK KÖKLENDİRME SİSTEMİNDE ORTAM NEMİNİN SENSÖRLERLE HASSAS KONTROLÜ Murat ÇAĞLAR Yüksek Lisans Tezi, Tarım Makinaları Anabilim Dalı Tez Danışmanı: Doç. Dr. Saadettin YILDIRIM 2014, 65 sayfa

Detaylı

Inventory of LCPs in Turkey LCP Database explained and explored

Inventory of LCPs in Turkey LCP Database explained and explored Inventory of LCPs in Turkey LCP Database explained and explored Hakan Hatipoglu Antalya, 9 October 2015 Requirements and specifications (TOR) Web based database application that will: Support Inventory

Detaylı

TEST RESULTS UFED, XRY and SIMCON

TEST RESULTS UFED, XRY and SIMCON TEST RESULTS UFED, XRY and SIMCON Test material : SIM card Tested software : UFED 3.6, XRY 6.5, SIMcon v1.2 Expected results : Proper extraction of SMS messages Date of the test : 02.04.2013 Note : The

Detaylı

YEDİTEPE ÜNİVERSİTESİ MÜHENDİSLİK VE MİMARLIK FAKÜLTESİ

YEDİTEPE ÜNİVERSİTESİ MÜHENDİSLİK VE MİMARLIK FAKÜLTESİ MÜHENDİSLİK VE MİMARLIK FAKÜLTESİ STAJ DEFTERİ TRAINING DIARY Adı, Soyadı Name, Lastname : ÖĞRENCİ NİN STUDENT S No ID Bölümü Department : : Fotoğraf Photo Öğretim Yılı Academic Year : Academic Honesty

Detaylı

Yaz okulunda (2014 3) açılacak olan 2360120 (Calculus of Fun. of Sev. Var.) dersine kayıtlar aşağıdaki kurallara göre yapılacaktır:

Yaz okulunda (2014 3) açılacak olan 2360120 (Calculus of Fun. of Sev. Var.) dersine kayıtlar aşağıdaki kurallara göre yapılacaktır: Yaz okulunda (2014 3) açılacak olan 2360120 (Calculus of Fun. of Sev. Var.) dersine kayıtlar aşağıdaki kurallara göre yapılacaktır: Her bir sınıf kontenjanı YALNIZCA aşağıdaki koşullara uyan öğrenciler

Detaylı

AKDENİZ ÜNİVERSİTESİ MÜHENDİSLİK FAKÜLTESİ ÇEVRE MÜHENDİSLİĞİ BÖLÜMÜ ÇEV181 TEKNİK İNGİLİZCE I

AKDENİZ ÜNİVERSİTESİ MÜHENDİSLİK FAKÜLTESİ ÇEVRE MÜHENDİSLİĞİ BÖLÜMÜ ÇEV181 TEKNİK İNGİLİZCE I AKDENİZ ÜNİVERSİTESİ MÜHENDİSLİK FAKÜLTESİ ÇEVRE MÜHENDİSLİĞİ BÖLÜMÜ ÇEV181 TEKNİK İNGİLİZCE I Dr. Öğr. Üyesi Firdes YENİLMEZ KTS Kredisi 3 (Kurumsal Saat: 2 Uygulama Saat: 1) Ders Programı Pazartesi 09:30-12:20

Detaylı

ANKARA ÜNİVERSİTESİ FEN BİLİMLERİ ENSTİTÜSÜ DÖNEM PROJESİ TAŞINMAZ DEĞERLEMEDE HEDONİK REGRESYON ÇÖZÜMLEMESİ. Duygu ÖZÇALIK

ANKARA ÜNİVERSİTESİ FEN BİLİMLERİ ENSTİTÜSÜ DÖNEM PROJESİ TAŞINMAZ DEĞERLEMEDE HEDONİK REGRESYON ÇÖZÜMLEMESİ. Duygu ÖZÇALIK ANKARA ÜNİVERSİTESİ FEN BİLİMLERİ ENSTİTÜSÜ DÖNEM PROJESİ TAŞINMAZ DEĞERLEMEDE HEDONİK REGRESYON ÇÖZÜMLEMESİ Duygu ÖZÇALIK GAYRİMENKUL GELİŞTİRME VE YÖNETİMİ ANABİLİM DALI ANKARA 2018 Her hakkı saklıdır

Detaylı

MOZAİK SANATI ANTAKYA VE ZEUGMA MOZAİKLERİNİN RESİM ANALİZLERİ MEHMET ŞAHİN. YÜKSEK LİSANS TEZİ Resim Ana Sanat Dalı Danışman: Doç.

MOZAİK SANATI ANTAKYA VE ZEUGMA MOZAİKLERİNİN RESİM ANALİZLERİ MEHMET ŞAHİN. YÜKSEK LİSANS TEZİ Resim Ana Sanat Dalı Danışman: Doç. MOZAİK SANATI ANTAKYA VE ZEUGMA MOZAİKLERİNİN RESİM ANALİZLERİ MEHMET ŞAHİN Yüksek Lisans Tezi Eskişehir 2010 MOZAİK SANATI ANTAKYA VE ZEUGMA MOZAİKLERİNİN RESİM ANALİZLERİ MEHMET ŞAHİN YÜKSEK LİSANS TEZİ

Detaylı

EGE UNIVERSITY ELECTRICAL AND ELECTRONICS ENGINEERING COMMUNICATION SYSTEM LABORATORY

EGE UNIVERSITY ELECTRICAL AND ELECTRONICS ENGINEERING COMMUNICATION SYSTEM LABORATORY EGE UNIVERSITY ELECTRICAL AND ELECTRONICS ENGINEERING COMMUNICATION SYSTEM LABORATORY INTRODUCTION TO COMMUNICATION SYSTEM EXPERIMENT 4: AMPLITUDE MODULATION Objectives Definition and modulating of Amplitude

Detaylı

TEK KADEMELİ GAZ BRÜLÖRLERİ SINGLE STAGE GAS BURNERS

TEK KADEMELİ GAZ BRÜLÖRLERİ SINGLE STAGE GAS BURNERS Lİ GAZ BRÜLÖRLERİ SINGLE STAGE GAS BURNERS Doğru seçimle başlamak Starting the right selection ÜRET GAZ BRÜLÖRLERİ 30 7500 kw TS EN 676 + A2 çerçevesinde CE 1312 sertifikasyonu ile üretilen üflemeli tip

Detaylı

ORANSAL GAZ BRÜLÖRLERİ MODULATED GAS BURNERS

ORANSAL GAZ BRÜLÖRLERİ MODULATED GAS BURNERS GAZ BRÜLÖRLERİ MODULATED GAS BURNERS Doğru seçimle başlamak Starting the right selection ÜRET GAZ BRÜLÖRLERİ 30 7500 kw TS EN 676 + A2 çerçevesinde CE 1312 sertifikasyonu ile üretilen üflemeli tip Üret

Detaylı

ÖNEMLİ PREPOSİTİONAL PHRASES

ÖNEMLİ PREPOSİTİONAL PHRASES ÖNEMLİ PREPOSİTİONAL PHRASES Bu liste YDS için Önemli özellikle seçilmiş prepositional phrase leri içerir. 72 adet Preposition 2 adet Toplam 74 adet Bu doküman, YDS ye hazırlananlar için dinamik olarak

Detaylı

Near East University. Graduate School of Educational Sciences. Department of English Language Teaching

Near East University. Graduate School of Educational Sciences. Department of English Language Teaching Near East University Graduate School of Educational Sciences Department of English Language Teaching THE ATTITUDES OF TEACHERS AND STUDENTS TOWARDS THE IMPORTANCE OF TEACHING CULTURAL ASPECTS WITHIN ENGLISH

Detaylı

INSPIRE CAPACITY BUILDING IN TURKEY

INSPIRE CAPACITY BUILDING IN TURKEY Ministry of Environment and Urbanization General Directorate of Geographical Information Systems INSPIRE CAPACITY BUILDING IN TURKEY Section Manager Department of Geographical Information Agenda Background

Detaylı

Draft CMB Legislation Prospectus Directive

Draft CMB Legislation Prospectus Directive Draft CMB Legislation Prospectus Directive Ayşegül Ekşit, SPK / CMB 1 Kapsam İzahname Konulu Taslaklar İzahname Yayınlama Zorunluluğu ve Muafiyetler İzahnamenin Onay Süreci İzahname Standartları İzahnamenin

Detaylı

Performans Tabloları Yalınkat Camlar

Performans Tabloları Yalınkat Camlar Performans Tabloları Yalınkat Camlar Kaplamalı Yüzey Gün Işığı Soğurma Güneş Enerjisi Direkt Toplam Gölgeleme Isı (U Değeri) W/m 2 K Gümüş #1 38 33 27 30 43 50 0,57 5,7 #2 38 27 20 38 43 52 0,59 5,7 Yeşil

Detaylı

DOKUZ EYLUL UNIVERSITY FACULTY OF ENGINEERING OFFICE OF THE DEAN COURSE / MODULE / BLOCK DETAILS ACADEMIC YEAR / SEMESTER

DOKUZ EYLUL UNIVERSITY FACULTY OF ENGINEERING OFFICE OF THE DEAN COURSE / MODULE / BLOCK DETAILS ACADEMIC YEAR / SEMESTER Offered by: Bilgisayar Mühendisliği Course Title: COMPUTER PROGRAMMING Course Org. Title: COMPUTER PROGRAMMING Course Level: Course Code: CME 0 Language of Instruction: İngilizce Form Submitting/Renewal

Detaylı

Dersin Kodu Dersin Adı Dersin Türü Yıl Yarıyıl AKTS

Dersin Kodu Dersin Adı Dersin Türü Yıl Yarıyıl AKTS Dersin Kodu Dersin Adı Dersin Türü Yıl Yarıyıl AKTS 507004832007 KALİTE KONTROLÜ Seçmeli 4 7 3 Dersin Amacı Günümüz sanayisinin rekabet ortamında kalite kontrol gittikçe önem kazanan alanlardan birisi

Detaylı

Gelir Dağılımı ve Yoksulluk

Gelir Dağılımı ve Yoksulluk 19 Decembre 2014 Gini-coefficient of inequality: This is the most commonly used measure of inequality. The coefficient varies between 0, which reflects complete equality and 1, which indicates complete

Detaylı

ANALYSIS OF PREPAREDNESS AND RESPONSE TO EARTHQUAKE RISK OF BEŞĐKTAŞ DISTRICT USING GIS

ANALYSIS OF PREPAREDNESS AND RESPONSE TO EARTHQUAKE RISK OF BEŞĐKTAŞ DISTRICT USING GIS i ANALYSIS OF PREPAREDNESS AND RESPONSE TO EARTHQUAKE RISK OF BEŞĐKTAŞ DISTRICT USING GIS by Ayşegül Özturan Akşit B.S., Geodesy and Photogrammetry Engineering Yıldız Technical University, 2005 Submitted

Detaylı

by Karin Şeşetyan BS. In C.E., Boğaziçi University, 1994

by Karin Şeşetyan BS. In C.E., Boğaziçi University, 1994 A PROBABILISTIC ASSESSMENT OF THE SEISMIC HAZARD IN THE CAUCASUS IN TERMS OF SPECTRAL VALUES by Karin Şeşetyan BS. In C.E., Boğaziçi University, 1994 Submitted to Kandilli Observatory and Earthquake Research

Detaylı

Cases in the Turkish Language

Cases in the Turkish Language Fluentinturkish.com Cases in the Turkish Language Grammar Cases Postpositions, circumpositions and prepositions are the words or morphemes that express location to some kind of reference. They are all

Detaylı

a, ı ı o, u u e, i i ö, ü ü

a, ı ı o, u u e, i i ö, ü ü Possessive Endings In English, the possession of an object is described by adding an s at the end of the possessor word separated by an apostrophe. If we are talking about a pen belonging to Hakan we would

Detaylı

BİR BASKI GRUBU OLARAK TÜSİADTN TÜRKİYE'NİN AVRUPA BİRLİĞl'NE TAM ÜYELİK SÜRECİNDEKİ ROLÜNÜN YAZILI BASINDA SUNUMU

BİR BASKI GRUBU OLARAK TÜSİADTN TÜRKİYE'NİN AVRUPA BİRLİĞl'NE TAM ÜYELİK SÜRECİNDEKİ ROLÜNÜN YAZILI BASINDA SUNUMU T.C. ANKARA ÜNİVERSİTESİ SOSYAL BİLİMLER ENSTİTÜSÜ HALKLA İLİŞKİLER VE TANITIM ANABİLİM DALI BİR BASKI GRUBU OLARAK TÜSİADTN TÜRKİYE'NİN AVRUPA BİRLİĞl'NE TAM ÜYELİK SÜRECİNDEKİ ROLÜNÜN YAZILI BASINDA

Detaylı

MATEMATİK BÖLÜMÜ BÖLÜM KODU:3201

MATEMATİK BÖLÜMÜ BÖLÜM KODU:3201 BÖLÜM KODU:01 011-01 01.Yarıyıl Dersleri 0.Yarıyıl Dersleri MTK 101 Analiz I Analysis I 4 1 5 6 MTK 10 Analiz II Analysis II 4 1 5 6 MTK 11 Lineer Cebir I Linear Algebra I 1 4 MTK 1 Lineer Cebir II Linear

Detaylı

Student (Trainee) Evaluation [To be filled by the Supervisor] Öğrencinin (Stajyerin) Değerlendirilmesi [Stajyer Amiri tarafından doldurulacaktır]

Student (Trainee) Evaluation [To be filled by the Supervisor] Öğrencinin (Stajyerin) Değerlendirilmesi [Stajyer Amiri tarafından doldurulacaktır] Student (Trainee) Evaluation [To be filled by the Supervisor] Öğrencinin (Stajyerin) Değerlendirilmesi [Stajyer Amiri tarafından doldurulacaktır] Student s Name & Surname (Öğrencinin Adı & Soyadı): PERSONALITY

Detaylı

: Shower Unit (Flat) : Kompakt Duș Ünitesi (Flat)

: Shower Unit (Flat) : Kompakt Duș Ünitesi (Flat) Veo Description Tanım : Shower Unit (Flat) : Kompakt Duș Ünitesi (Flat) Left/Sol Right/Sağ Size / Ebat (cm) : 190x90 Depth / Derinlik (cm) : 3,5 Height / Yükseklik (cm) : 215 Weight / Ağırlık (kg) : min.

Detaylı

BBM Discrete Structures: Midterm 2 Date: , Time: 16:00-17:30. Question: Total Points: Score:

BBM Discrete Structures: Midterm 2 Date: , Time: 16:00-17:30. Question: Total Points: Score: BBM 205 - Discrete Structures: Midterm 2 Date: 8.12.2016, Time: 16:00-17:30 Ad Soyad / Name: Ögrenci No /Student ID: Question: 1 2 3 4 5 6 7 Total Points: 12 22 10 10 15 16 15 100 Score: 1. (12 points)

Detaylı

.. ÜNİVERSİTESİ UNIVERSITY ÖĞRENCİ NİHAİ RAPORU STUDENT FINAL REPORT

.. ÜNİVERSİTESİ UNIVERSITY ÖĞRENCİ NİHAİ RAPORU STUDENT FINAL REPORT .. ÜNİVERSİTESİ UNIVERSITY... /... AKADEMİK YILI... DÖNEMİ... /... ACADEMIC YEAR... TERM ÖĞRENCİ NİHAİ RAPORU STUDENT FINAL REPORT Deneyimleriniz hakkındaki bu rapor, Mevlana Değişim Programı nın amacına

Detaylı

ASSESSMENT OF SUDAN-NYALA City s WATER HEALTH IN UNUSUAL LIFE

ASSESSMENT OF SUDAN-NYALA City s WATER HEALTH IN UNUSUAL LIFE ASSESSMENT OF SUDAN-NYALA City s WATER HEALTH IN UNUSUAL LIFE *Hasan Hüseyin EKER *Sanaa İSHAG **Eyup DEBİK **Ahmet DOGAN * Ceyda ACAR *** Ahmed Beraka *Bezmialem Vakİf University - School of Medicine

Detaylı

YEDİTEPE ÜNİVERSİTESİ MÜHENDİSLİK VE MİMARLIK FAKÜLTESİ

YEDİTEPE ÜNİVERSİTESİ MÜHENDİSLİK VE MİMARLIK FAKÜLTESİ ÖĞRENCİ NİN STUDENT S YEDİTEPE ÜNİVERSİTESİ STAJ DEFTERİ TRAINING DIARY Adı, Soyadı Name, Lastname : No ID Bölümü Department : : Fotoğraf Photo Öğretim Yılı Academic Year : Academic Honesty Pledge I pledge

Detaylı

Bağlaç 88 adet P. Phrase 6 adet Toplam 94 adet

Bağlaç 88 adet P. Phrase 6 adet Toplam 94 adet ÖNEMLİ BAĞLAÇLAR Bu liste YDS için Önemli özellikle seçilmiş bağlaçları içerir. 88 adet P. Phrase 6 adet Toplam 94 adet Bu doküman, YDS ye hazırlananlar için dinamik olarak oluşturulmuştur. 1. although

Detaylı

NOKTA VE ÇİZGİNİN RESİMSEL ANLATIMDA KULLANIMI Semih KAPLAN SANATTA YETERLİK TEZİ Resim Ana Sanat Dalı Danışman: Doç. Leyla VARLIK ŞENTÜRK Eylül 2009

NOKTA VE ÇİZGİNİN RESİMSEL ANLATIMDA KULLANIMI Semih KAPLAN SANATTA YETERLİK TEZİ Resim Ana Sanat Dalı Danışman: Doç. Leyla VARLIK ŞENTÜRK Eylül 2009 NOKTA VE ÇİZGİNİN RESİMSEL ANLATIMDA KULLANIMI SANATTA YETERLİK TEZİ Resim Ana Sanat Dalı Danışman: Doç. Leyla VARLIK ŞENTÜRK Eylül 2009 Anadolu Üniversitesi Güzel Sanatlar Enstitüsü Eskişehir RESİMSEL

Detaylı

Öğrencilere, endüstriyel fanları ve kullanım alanlarını tanıtmak, endüstriyel fan teknolojisini öğretmektir.

Öğrencilere, endüstriyel fanları ve kullanım alanlarını tanıtmak, endüstriyel fan teknolojisini öğretmektir. Ders Öğretim Planı Dersin Kodu Dersin Adı Dersin Türü Yıl Yarıyıl AKTS 507004962014 ENDÜSTRİYEL FANLAR Seçmeli 4 8 3 Dersin Amacı Öğrencilere, endüstriyel fanları ve kullanım alanlarını tanıtmak, endüstriyel

Detaylı

Prof. Dr. N. Lerzan ÖZKALE

Prof. Dr. N. Lerzan ÖZKALE ERASMUS + YÜKSEKÖĞRETİM YIL SONU DEĞERLENDİRME TOPLANTISI Akdeniz Üniversitesi, Antalya AKADEMİK TANINMA Prof. Dr. N. Lerzan ÖZKALE İstanbul Teknik Üniversitesi ve Kadir Has Üniversitesi 21 Aralık 2017

Detaylı

Privatization of Water Distribution and Sewerages Systems in Istanbul Assoc. Prof. Dr. Eyup DEBIK Menekse Koral Isik

Privatization of Water Distribution and Sewerages Systems in Istanbul Assoc. Prof. Dr. Eyup DEBIK Menekse Koral Isik Privatization of Water Distribution and Sewerages Systems in Istanbul Assoc. Prof. Dr. Eyup DEBIK Menekse Koral Isik Yildiz Technical University, Environmental Engineering Dept., Istanbul-Turkey Aim and

Detaylı

BOĞAZİÇİ UNIVERSITY KANDİLLİ OBSERVATORY and EARTHQUAKE RESEARCH INSTITUTE GEOMAGNETISM LABORATORY

BOĞAZİÇİ UNIVERSITY KANDİLLİ OBSERVATORY and EARTHQUAKE RESEARCH INSTITUTE GEOMAGNETISM LABORATORY Monthly Magnetic Bulletin May 2015 BOĞAZİÇİ UNIVERSITY KANDİLLİ OBSERVATORY and EARTHQUAKE RESEARCH INSTITUTE GEOMAGNETISM LABORATORY http://www.koeri.boun.edu.tr/jeomanyetizma/ Magnetic Results from İznik

Detaylı

EKONOMİZER ECONOMIZER

EKONOMİZER ECONOMIZER EKONOMİZER EKONOMİZER KONEKO EKONOMİZERİ GENEL BİLGİ / KONEKO GENERAL INFORMATION Koneko Ekonomizer baca gazlarının atık ısısından yararlanarak, buhar kazanları, kızgın yağ kazanları, sıcak ve kızgın su

Detaylı

L2 L= nh. L4 L= nh. C2 C= pf. Term Term1 Num=1 Z=50 Ohm. Term2 Num=2 Z=50 Oh. C3 C= pf S-PARAMETERS

L2 L= nh. L4 L= nh. C2 C= pf. Term Term1 Num=1 Z=50 Ohm. Term2 Num=2 Z=50 Oh. C3 C= pf S-PARAMETERS 1- Design a coupled line 5th order 0.5 db equal-ripple bandpass filter with the following characteristics: Zo = 50 ohm, band edges = 3 GHz and 3.5 GHz, element values of LPF prototype are with N = 5: g1

Detaylı

YUVARLAK TAVAN ANEMOSTADI. Round Ceiling Diffuser

YUVARLAK TAVAN ANEMOSTADI. Round Ceiling Diffuser YUVARLAK TAVAN ANEMOSTADI Round Ceiling Diffuser YUVARLAK TAVAN ANEMOSTADI ( ) ROUND CEILING DIFFUSER Yuvarlak Tavan Anemostadý Teknik Detaylarý Round Ceiling Diffuser Technical Details : Malzeme: Kullaným:

Detaylı

Inspection Report Muayene Raporu KARE MÜHENDİSLİK ÇEVRE TEKNOLOJİLERİ SAN. TİC. A.Ş. SOLAR WATER HUMANITARIAN PROJECT

Inspection Report Muayene Raporu KARE MÜHENDİSLİK ÇEVRE TEKNOLOJİLERİ SAN. TİC. A.Ş. SOLAR WATER HUMANITARIAN PROJECT Offer Nr / Teklif No TGK Order Nr / Sipariş No Register Nr / Kayıt No 17-IS-0537-01-G 712917258 17 - IR - 0248.R1 Inspection Report Muayene Raporu No. KARE MÜHENDİSLİK ÇEVRE TEKNOLOJİLERİ SAN. TİC. A.Ş.

Detaylı

OTOMOTİV SAN. TİC. LTD. ŞTİ. OTOMOTİV YEDEK PARÇA İMALATI AUTOMOTIVE SPARE PART MANUFACTURING

OTOMOTİV SAN. TİC. LTD. ŞTİ.   OTOMOTİV YEDEK PARÇA İMALATI AUTOMOTIVE SPARE PART MANUFACTURING OTOMOTİV SAN. TİC. LTD. ŞTİ. www.ozaksen.com.tr OTOMOTİV YEDEK PARÇA İMALATI AUTOMOTIVE SPARE PART MANUFACTURING ÜRÜNLERİMİZ OUR PRODUCTS INTERCOOL BAĞLANTI BORULARI INTERCOOL CONNECTION PIPES... 4 YAĞ

Detaylı

Virtualmin'e Yeni Web Sitesi Host Etmek - Domain Eklemek

Virtualmin'e Yeni Web Sitesi Host Etmek - Domain Eklemek Yeni bir web sitesi tanımlamak, FTP ve Email ayarlarını ayarlamak için yapılması gerekenler Öncelikle Sol Menüden Create Virtual Server(Burdaki Virtual server ifadesi sizi yanıltmasın Reseller gibi düşünün

Detaylı

THE EUROPEAN NEIGHBOURHOOD POLICY: AN EFFECTIVE FOREIGN POLICY TOOL FOR THE EUROPEAN UNION?

THE EUROPEAN NEIGHBOURHOOD POLICY: AN EFFECTIVE FOREIGN POLICY TOOL FOR THE EUROPEAN UNION? THE EUROPEAN NEIGHBOURHOOD POLICY: AN EFFECTIVE FOREIGN POLICY TOOL FOR THE EUROPEAN UNION? A THESIS SUBMITTED TO THE GRADUATE SCHOOL OF SOCIAL SCIENCES OF MIDDLE EAST TECHNICAL UNIVERSITY BY BURCU MAZLUM

Detaylı

$5$ù7,50$ (%(/ø. gö5(1&ø/(5ø1ø1 *g5(9 7$1,0/$5, 9( <(7(5/ø/ø. $/$1/$5,1$ *g5(.(1'ø/(5ø1ø '(ö(5/(1'ø50(/(5ø g]hq (VUD.$5$0$1 + O\D 2.

$5$ù7,50$ (%(/ø. gö5(1&ø/(5ø1ø1 *g5(9 7$1,0/$5, 9( <(7(5/ø/ø. $/$1/$5,1$ *g5(.(1'ø/(5ø1ø '(ö(5/(1'ø50(/(5ø g]hq (VUD.$5$0$1 + O\D 2. ÖZET Amaç: Bu araştırma, Sağlık Yüksekokulları Ebelik Bölümü son sınıf öğrencilerinin, ebelerin Sağlık Bakanlığı görev tanımları ve Uluslararası Ebeler Konfederasyonu yeterlilik alanlarına göre kendilerini

Detaylı

Dersin Kodu Dersin Adı Dersin Türü Yıl Yarıyıl AKTS 507004092007 MAKİNA PROJESİ II Zorunlu 4 7 4

Dersin Kodu Dersin Adı Dersin Türü Yıl Yarıyıl AKTS 507004092007 MAKİNA PROJESİ II Zorunlu 4 7 4 Ders Öğretim Planı Dersin Kodu Dersin Adı Dersin Türü Yıl Yarıyıl AKTS 507004092007 MAKİNA PROJESİ II Zorunlu 4 7 4 Dersin Seviyesi Lisans Dersin Amacı Dersin amacı Makina Mühendisliği bölümü Lisans öğrencilerine

Detaylı

ENG ACADEMIC YEAR SPRING SEMESTER FRESHMAN PROGRAM EXEMPTION EXAM

ENG ACADEMIC YEAR SPRING SEMESTER FRESHMAN PROGRAM EXEMPTION EXAM ENG111 2016-2017 ACADEMIC YEAR SPRING SEMESTER FRESHMAN PROGRAM EXEMPTION EXAM Exam Type Date / Classes / Time Written Thursday, September 22 nd, 2016 Classes & Time to be announced on September 20th.

Detaylı

İÇİNDEKİLER. Sayfa ÖNSÖZ... II ÖZET... VIII SUMMARY...IX ŞEKİL LİSTESİ... X TABLO LİSTESİ...XIX SEMBOL LİSTESİ...XX

İÇİNDEKİLER. Sayfa ÖNSÖZ... II ÖZET... VIII SUMMARY...IX ŞEKİL LİSTESİ... X TABLO LİSTESİ...XIX SEMBOL LİSTESİ...XX İÇİNDEKİLER Sayfa ÖNSÖZ... II ÖZET... VIII SUMMARY...IX ŞEKİL LİSTESİ... X TABLO LİSTESİ...XIX SEMBOL LİSTESİ...XX 1. GENEL BİLGİLER...1 1.1. Giriş...1 1.2. Geçmişte Yapılan Çalışmalar...2 1.3. Bu Çalışmanın

Detaylı

Determinants of Education-Job Mismatch among University Graduates

Determinants of Education-Job Mismatch among University Graduates EMLT Project Determinants of Education-Job Mismatch among University Graduates Yılmaz Kılıçaslan Anadolu University ykilicaslan@anadolu.edu.tr Nilgün Çağlarırmak Uslu Anadolu University ncaglarirmak@anadolu.edu.tr

Detaylı