Unlicensed Electricity Production in Turkey Özer KARA Seul EltemTek Energy Systems A.Ş. Project Manager
About Seul EltemTek A.Ş.
Company Structure Seul Group of Companies Production Partner with China Sunergy (Nasdaq:CSUN). First PV cell production facility in Turkey (150MW). Biggest PV module production facility in Turkey (300MW). Distribution Wholesale distribution of high-quality top-class PV power equipment. Investment Invests in Renewable Energy Projects. EPC Services Founded Seul EltemTek A.Ş. with EltemTek, a partnership of TEİAŞ. 9.4.2014 PV Power Plants in Turkey - İstanbul 3
Company Structure Eltem-Tek Established in 1983 with the Council of Ministers decision 47% owned by TEİAŞ Over 300 employees One of the biggest system integrators Fields of activity; Electric power plants, O&M Services (over 600 MW) Privatization consultancy System analysis auditing Environmental engineering services Auditing and expropriation (over 2000 km of transmission lines) Transmission and Distribution services
Company Structure 9.4.2014 PV Power Plants in Turkey - İstanbul 5
Electricity Sector in Turkey
Electricity Sector in Turkey Production Transmission Distribution Retail Sales Electricity Production Co.(EÜAŞ) Turkish Electricity Trade and Commitment Co.(TETAŞ) Independent Energy Producers Autoproducers and Autoproducer Groups Turkish Electricity Transmission Co. (TEİAŞ) Turkish Electricity Distribution Co. (TEDAŞ) Private Distribution Companies Industrial Zones (OSB) Turkish Electricity Distribuiton Co. (TEDAŞ) Private Distribution Companies Companies with Wholesale Licenses (Ref. Bilal ŞİMŞEK, TEDAŞ) 9.4.2014 PV Power Plants in Turkey - İstanbul 7
Historical Development and Current Status 1970 Permission for the Private Sector to enter the Electricity Market (1984) TEK (Production, Transmission, Distribution) 1994 Seperation of distribution from production & transmission TEAŞ (Production & Transmission) TEDAŞ (Distribution) 2001 Division of TEAŞ EÜAŞ (Prod.) TEİAŞ (Trans.) TETAŞ (Wholesale) 2004 Founding of local distribution companies Start of privatization for distribution 21 Dist. Zones (Distribution) 2013 As of September 2013, all 21 local distribution companies are privatized. (Ref. Bilal ŞİMŞEK, TEDAŞ) 9.4.2014 PV Power Plants in Turkey - İstanbul 8
Kırklareli Tekirdağ Edirne Çanakkale 13. Kütahya Manisa Ġstanbul Anadolu Y. Bartın Zonguldak Karabük Kocaeli Düzce Yalova Bolu Sakarya 15 Bilecik 9 Bursa Balıkesir EskiĢehir 11 12 UĢak Ġzmir Aydın Denizli Muğla 17 Ġstanbul Avrupa Y. 19 14 16 Afyon Isparta Ankara Konya 8 Local Sinop Electricity Distribution Companies in Kastamonu Artvin Ardahan Çankırı 21 Çorum Tokat Kırıkkale Yozgat KırĢehir NevĢehir Aksaray Niğde Samsun Amasya Kayseri Ordu Giresun Sivas Malatya K.MaraĢ Adıyaman Trabzon GümüĢhane Bayburt Burdur Adana Karaman Osmaniye Gaziantep Antalya ġanlıurfa 10 Mersin Kilis 18 7 6 20 5 Rize Erzincan Tunceli Bingöl Elazığ 1 4 Kars Erzurum 3 Diyarbakır Batman Mardin Ağrı MuĢ Bitlis Siirt ġırnak 2 Turkey Iğdır Van Hakkari Hatay 1. Dicle E. Dağıtım A.Ş. / Dicle Elec. Distr. Co. (Diyarbakır, Mardin, Siirt, Şanlıurfa, Batman, Şırnak) 2. Vangölü Elektrik Dağıtım A.Ş. / Vangölü Electricity Distribution Co. (Bitlis, Hakkari, Muş, Van) 3. Aras E. Dağıtım A.Ş. / Aras E. Distr. Co. (Ağrı, Erzincan, Erzurum, Kars, Bayburt, Ardahan, Iğdır) 4. Çoruh Elektrik Dağıtım A.Ş. / Çoruh E. Distribution Co. (Artvin, Giresun, Gümüşhane, Rize, Trabzon) 5. Fırat Elektrik Dağıtım A.Ş. / Fırat Electricity Distribution Co. (Bingöl, Elazığ, Malatya, Tunceli) 6. Çamlıbel Elektrik Dağıtım A.Ş. / Çamlıbel Electricity Distribution Co. (Sivas, Tokat, Yozgat) 7. Toroslar E. Dağıtım A.Ş. / Toroslar E. Distr. Co. (Adana, Gaziantep, Hatay, Mersin, Kilis, Osmaniye) 8. Meram E. Dağıtım A.Ş. / Meram E. Distr. Co. (Kırşehir, Konya, Nevşehir, Niğde, Aksaray, Karaman) 9. Başkent E.D.A.Ş. / Başkent E.D.Co. (Ankara,Çankırı,Kastamonu,Zonguldak,Kırıkkale,Bartın,Karabük) 10. Akdeniz Elektrik Dağıtım A.Ş. / Akdeniz Electricity Distribution Co. (Antalya, Burdur, Isparta) 11. Gediz Elektrik Dağıtım A.Ş. / Gediz Electricity Distribution Co. (İzmir, Manisa) 12. Uludağ Elektrik Dağıtım A.Ş. / Uludağ Electricity Distribution Co. (Balıkesir, Bursa, Çanakkale, Yalova) 13. Trakya Elektrik Dağıtım A.Ş. / Trakya Electricity Distribution Co. (Edirne, Kırklareli, Tekirdağ) 14. İstanbul Anad.Y. E.Dağ. A.Ş. / İstanbul Anatolian Side E.D.Co. (İstanbul ili Anad.Yakası / İstanbul Anatolian Side) 15. Sakarya Elektrik Dağıtım A.Ş. / Sakarya Electricity Distribution Co. (Bolu, Kocaeli, Sakarya, Düzce) 16. Osmangazi Elektrik Dağıtım A.Ş. / Osmangazi E. Distr. Co. (Afyonkarahisar, Bilecik, Eskişehir, Kütahya, Uşak) 17. Boğaziçi Elektrik Dağ. A.Ş. / Boğaziçi Elec. Distribution Co. (İstanbul ili Avrupa Yakası / İstanbul European Side) 18. Kayseri ve Civarı Elektrik T.A.Ş. / Kayseri and Its Vicinity Electricity Turkish Inc. Co. (Kayseri) 19. Aydem Elektrik Dağıtım A.Ş. / Aydem Electricity Distribution Co. (Aydın, Denizli, Muğla) 20. Akedaş Elektrik Dağıtım A.Ş. / Akedaş Electricity Distribution Co. (Adıyaman, Kahramanmaraş) 21. Yeşilırmak Elektrik Dağıtım A.Ş. / Yeşilırmak Electricity Distribution Co. (Amasya, Çorum, Ordu, Samsun, Sinop) 9.4.2014 PV Power Plants in Turkey - İstanbul 9
Unlicensed Electricity Production
Progress Date Action 10 March 2005 Publication of the Law Nr. 5346 (Renewable Energy Law) 26 July 2008 Changes in Law Nr. 4628 (Elelctricity Market Law) September 2008 First regulation draft by EPDK 23 January 2009 2nd revision by EPDK 13 July 2009 3rd revision by EPDK 3 December 2010 First official publication of the Regulation for Unlicensed Electricity Production 29 December 2010 Publication of the Law Nr. 6094 (changes in the Law Nr. 5346, Renewable Energy Law) which forced some of the clauses of the regulation to be changed 21 July 2011 Re-publication of the Regulation for Unlicensed Electricity Production 10 March 2012 Publication of the Announcement for the Regulation for Unlicensed Electricity Production and the Regulation for Unlicensed Electricity Production 14 March 2013 Publication of the Law Nr. 6446 (Electricity Market Law) 02 October 2013 Publication of the Announcement for the Regulation for Unlicensed Electricity Production and the Regulation for Unlicensed Electricity Production, 2nd version 9.4.2014 PV Power Plants in Turkey - İstanbul 11
General Terms One needs to be a consumer in order to be able to establish a power production plant The power plant has to be in the same distribution area (the consumer and the producer have to be at the same place or at different places but in the same distribution area) The limit for the RE power plant for each consumption point will be 1 MW in total For Wind and Solar Power Plants, connection capacities for each transformer station will be allocated accordingly by the distribution company until the total power allowed reaches 2 MW Once the 2 MW capacity limit is reached, the distribution company asks TEİAŞ for capacity approval 9.4.2014 PV Power Plants in Turkey - İstanbul 12
General Terms (ctd.) Power plants of installed power equal or less than 5 kw may be connected monophase to the LV grid. Power plants of more than 5 kw can only be connected tri-phase. LV connections are limited to 30% of the transformer. Applications to the distribution company will be collected monthly and evaluated the following month. Priorities during evaluating the applications; Renewables, Co-generation plants, Projects which have consumption-production on the same location, First-time applications or applications which haven t been rejected, Projects with higher last year annual consumption than the other applications, Application time. 9.4.2014 PV Power Plants in Turkey - İstanbul 13
Standards Power Plant Characteristic 1-ph 3-ph w/ phase current < 16A Standart TS EN 50438 phase current > 16A and LV connection CLC/FprTS 50549-1:2011 phase current > 16A and HV connection CLC/FprTS 50549-2:2011 9.4.2014 PV Power Plants in Turkey - İstanbul 14
FIT (Renewable Energy Law Nr. 5346) Plant FIT-1 ($c/kwh) (for 10 years) FIT-2 (Max. amount of extra incentive due to local produced equipment) ($c/kwh) (for 5 years) Max. Total Incentive ($c/kwh) Hydro 7,3 2,3 9,6 Wind 7,3 3,7 11 PV 13,3 6,7 20 CSP 13,3 9,2 22,5 Biomass 13,3 5,6 18,9 Geothermal 10,5 2,7 13,2 9.4.2014 PV Power Plants in Turkey - İstanbul 15
FIT Application Corporate and private energy producers will make use of the FIT for the excess energy if fed to the grid for ten years The distribution company obtaining the retail sales license in the area is obliged to buy the excess energy FIT is valid for power plants which will be connected to the grid and comissioned until 31/12/2020 Those who are entitled for the RES Support Mechanism can not leave the system within the same calendar year Power plants within the scope of this law have the priority when license applications are evaluated by EMRA (EPDK) 9.4.2014 PV Power Plants in Turkey - İstanbul 16
Application Steps Application to the distribution company Application Form Ownership Document or Rental Agreement for the land Single Line Diagram Application Fee Subscription number energy bill(s) Approval from Ministry of Agriculture (Non-agricultural Land Approval) Approval from Ministry of Environment (EIA Report) Invitation letter from the local distribution company Technical project approval application to TEDAŞ Conection Agreement with local distribution company Installation of the plant Temporary approval from authorized body (TEDAŞ) System Usage Agreement Commissioning of the plant 9.4.2014 PV Power Plants in Turkey - İstanbul 17
Road Map Application to Local Distribution Company Rejection Evaluation of the applications (first 20 days of the following month) «Invitation Letter for Connection Agreement» by Local Distribution Company. No Documents completed in 10 days? Yes Application documents complete? Technical project approval (within 90 + 90 days) and application to Local Distribution Company to sign connection agreement Notice from Local Distribution Company to complete the application documents No Yes Signing Connection Agreement within 30 days with Local Distribution Company (if documents are complete) Rejection and return of the documents No Application (including alternative) acceptable? Yes Construction of the power plant (1-2 years depending on the level of connection) Results (including alternative connection recommendations) announced on website by Local Distribution Company for 1 month. Temporary acceptance by authorized body and signing of the System Usage Agreement within 30 days Applicants with alternative connection recommendation applies writtenly to Local Distribution Company within 1 month to accept the recommendation. Comissioning of the power plant 9.4.2014 PV Power Plants in Turkey - İstanbul 18