Experiences with Self Consumption Projects Özgür SARPDAĞ Business Development Manager 9 th of April, Wednesday Solarpraxis PV Power Plants Turkey New Energy Renewable Energy
Index 1. ELSE Enerji References 2. Self Consumption Projects
References Engineering and Legal Approvals PROJECT NAME INVESTOR LACATION CAPACITY Işıkyuvar GES YBT Enerji Yatırım AŞ Antalya 1.150,00 kwp Işıkküre GES YBT Enerji Yatırım AŞ Antalya 1.150,00 kwp Ahmet Çelik GES Ahmet Çelik Konya 1.150,00 kwp Besa GES Besa İnşaat A.Ş Ankara 1.150,00 kwp RNT GES 1 RNT Enerji Üretim AŞ Niğde 1.000,00 kwp RNT GES 2 RNT Enerji Üretim AŞ Niğde 1.150,00 kwp Dormak GES Dormak Danışmanlık AŞ Ankara 1.150,00 kwp Taşova GES Taşova Sulama Birliği Amasya 1.000,00 kwp Multielektrik GES Multielektrik Solar Ltd. Antalya 13,00 kwp TOPLAM PROJE KAPASİTESİ: 8.913,00 kwp
References Turnkey Projects PROJECT NAME INVESTOR LACATION CAPACITY Hasçelik GES Has Çelik ve Halat AŞ Kayseri 1.150,00 kwp Beşler Tekstil GES Beşler Tekstil Sanayi AŞ Kayseri 1.150,00 kwp Özkoyuncu Maden. GES Özkoyuncu Madencilik AŞ Kayseri 1.012,00 kwp Özkoyuncu Enerji GES Özkoyuncu Enerji AŞ Kayseri 1.035,00 kwp Prokon AŞ GES Prokon İmalat ve Mon. AŞ Ankara 500,00 kwp Marka Grup GES Marka Grup Besi Çift. AŞ Sivas 500,00 kwp Dülükbaba GES Şehitkamil Belediyesi Gaziantep 40,00 kwp BriSA Academy GES Lassa Lastik San.veTic. AŞ İzmit 22,00 kwp Kayaşehir 17.Etap GES Toplu Konut İdaresi Bşk. İstanbul 62,00 kwp TOPLAM PROJE KAPASİTESİ: 5.471,00 kwp
Legal Infrastructure Unlicenced Electricity Production Regulation provides that real and legal persons fulfilling certain minimum legal requirements are exempt from the requirement of obtaining a license and establishing a company in order to generate electricity. With the Regulation, it is possible to establish a generating station or power plant, the installed power capacity of which is limited to a maximum of five hundred kilowatts based on renewable energy sources
Legal Infrastructure Unlicenced Electricity Production Regulation provides that real and legal persons fulfilling certain minimum legal requirements are exempt from the requirement of obtaining a license and establishing a company in order to generate electricity. With the Regulation, it is possible to establish a generating station or power plant, the installed power capacity of which is limited to a maximum of five hundred kilowatts based on renewable energy sources
Using Domestic Product If the mechanical and/or electro mechanical equipment which are used in power plants are based on renewable energy sources and which commenced operation before 31.12.2015, are manufactured in the country then, the prices set forth Schedule No.II attached to the law hereby are added to the prices set forth in the Schedule No.I for the electric energy given to the transmission or distribution system after being produced in such plants, for 5 years from the operation commencement date of the power plant.
Using Domestic Product Schedule No. II Type of Facility Domestic Production Domestic Contribution US Dolar Cent/kWh C Photovoltaic solar power based production facility 1 PV panel integration and solar structural mechanics production 0, 8 2 PV modules 1,3 3 Cells forming the PV Module 3,5 4 Inverter 0,6 5 Material focusing the solar light onto the PV Module 0,5
Net Metering Daily Cons. Metering Daily Prod. Metering Monthly Payment
Example 01 / Prokon Project Capacity: 500 kwp Estimated Production: 700.000 kwh/year Consumption of Factory: 1.750.000 kwh/year Solar Energy Percentage: %40 Selling to Grid: %0
Example 01 / Prokon Project
Example 01 / Prokon Project
Example 02 / Marka Grup Project Capacity: 500 kwp Estimated Production: 750.000 kwh/year Consumption of Farm: 350.000 kwh/year Solar Energy Percentage: %215 Selling to Grid: %53
Example 02 / Marka Grup Project
Example 02 / Marka Grup Project
Financial Situation Capacity: 500 kwp Estimated Production: 750.000 kwh/year FiT Value: 94.000 USD/year (gross return TEDAS cost added) Consum Value: 100.000 USD/year (electricity price: 0,29 TL/kwh without VAT)
Thanks for your attention Head Office: Anadolu Bulvarı 994 Sk. No:11/B PK: 06210 Aşağı Yahyalar / Yenimahalle /ANKARA Tel: +90(312) 394 60 98 Fax: +90(312) 332 33 03 Branch Office: Saray Mah. Dr. Adnan Büyükdeniz Cad. No:4 Akkom Ofis Park 2. Blok Kat:10 Ümraniye, İstanbul Tel: +90(216) 250 32 07 Fax: +90(216) 250 32 32 www.elseenerji.com